1.
Please provide your organization’s comments on Reliability-driven Projects Recommended for Approval.
The Public Advocates Office at the California Public Utilities Commission (Cal Advocates) provides these comments on the California Independent System Operator’s (CAISO) Draft 2023-2024 Transmission Plan issued on April 1, 2024 and stakeholder meeting on the draft Plan on April 9 2024. Cal Advocates is an independent ratepayer advocate with a mandate to obtain the lowest possible rates for utility services, consistent with reliable and safe service levels and the state’s environmental goals.[1]
A. Requests for Additional Project Information
- For the Gates 230/70 kilovolt (kV) Transformer Addition Project, Cal Advocates requests that CAISO and Pacific Gas and Electric Company (PG&E) provide additional information to explain the estimated project cost. The reported cost for the Gates 230/70 kV Transformer Addition Project is between $36 million and $72 million.[2] Based on the Participating Transmission Owner (PTO) per unit guide, an additional transformer bank at 230/70 kV should cost between $9.5 million and $19 million, with a 1.053 Escalation Rate applied for an in-service date of 2030.[3], [4] Given the cost difference between the proposed Gates 230 kV Transformer Addition project and the PTO per unit cost guide, PG&E should provide additional information to explain this difference.
- CAISO and the PTOs should provide the proposed circuit, tower, and terrain types as well as the proposed line length to be reconductored for all proposed projects to confirm that the reported project costs are reasonable. To explain, CAISO and PG&E did not provide sufficient information for the Reedley 70 kV Capacity Increase and Crazy Horse Canyon (CHCSS)-Salinas-Soledad #1 and #2 115 kV Line Reconductoring projects to compare their estimated costs with the cost information provided in the PTOs’ Final Per Unit Cost Guide.[5], [6] CAISO and PG&E, however, did provided the length of the lines to be reconductored for the Vaca-Plainfield 60 kV, the Rio Oso-W. Sacramento and Cortina #1 60 kV Line reconductoring projects.[7] Consistent with this practice, Cal Advocates requests that the CAISO and all the PTOs provide the circuit, tower and terrain types, and line lengths to be reconductored.
- For any proposed shunt reactors or other proposed new electrical grid equipment, Cal Advocates requests that CAISO and its PTOs provide a cost estimate. Cal Advocates makes this request because CAISO and PG&E cited just “lump sum” as the cost estimate for the proposed Shunt Reactors for the Diablo Canyon Area 230 kV High Voltage Mitigation project. [8]
B. CAISO Should Provide Participating Transmission Owners More Time to Develop Project Mitigation Recommendations.
At the September 27, 2023 reliability meeting, PG&E presented three conceptual projects and did not include final mitigation recommendations or project costs.[9] These projects are the Tejon Area, French Camp, and Spence 60 kV Area Reinforcement (now referred to as the Salinas Reinforcement project) projects. At the September 27, 2023, a PG&E representative explained that PG&E could not provide recommendations and costs for these projects because the existing one-month timeframe given in the Transmission Planning Process (TPP) to develop project solutions is not sufficient.[10] PG&E also continues to provide project cost estimates with a contingency of 100%.[11] A 100% contingency reflects a highly uncertain design. Cal Advocates requests that CAISO consider allowing at least six weeks for PTOs to develop project concepts in the TPP. Providing this additional time should allow the PTOs to provide complete project analysis and more accurate cost estimates for stakeholder review before projects are presented for approval.
C. Cal Advocates Requests Greater Transparency in the Transmission Planning Process
- All PTOs should provide their power flow results and alternative analysis for all proposed projects to demonstrate the project need and their determination of the least-cost best-fit option.
PG&E did not provide its power flow results or alternative analysis for the Rio Oso W. Sacramento and Cortina #1 60 kV line reconductoring projects at CAISO’s September 27, 2023 reliability meeting or its April 9, 2024 Draft Transmission Plan meeting. When CAISO and the PTOs present projects for approval without any information on the alternatives considered or power flow results, stakeholders are not provided the opportunity to understand the reason for potential mitigation solutions or to assess the benefits of alternatives. Cal Advocates requests that CAISO and its PTOs consistently provide their power flow and alternative analyses for all projects proposed for approval to provide transparency in the TPP.
- All PTOs should present their project alternatives in stakeholder meetings and include their analyses of grid enhancing technologies.
Cal Advocates appreciates CAISO’s consideration of the opportunities presented by grid enhancing technologies (GETs) in its Draft 2023-2024 Transmission Plan. As demonstrated through more than half a decade of research and case studies, GETs can enhance the capacity of existing lines and mitigate congestion at lower costs than traditional wire investment projects.[12], [13] For this reason, Cal Advocates recommends that CAISO and its PTOs demonstrate that they consider GETs options where applicable to address identified issues on the grid in their alternative analyses. If a GETs solution cannot be considered to address grid issues for a technical reason, Cal Advocates requests CAISO and PTOs provide the reason why GETs cannot be considered in their alternative analyses.
Since PG&E did not provide an alternative analysis for the Rio Oso W. Sacramento and Cortina #1 60 kV Line Reconductoring projects, Cal Advocates requests PG&E consider and analyze installing one to two four-hour batteries paired with a power flow device as an alternative to address the identified issues in these project areas.
- All PTOs should present their load data in a timely manner for consideration in the California Energy Commission’s annual load forecast.
It is critical that all PTOs share their load data with the CEC in a timely manner so that it can be assessed in the CEC’s Integrated Energy Policy Report (IEPR) proceeding. The IEPR proceeding is an existing process that is transparent and robust and should continue to be utilized to evaluate expected load growth including new load from the state’s transportation corridors. CAISO and the California Public Utilities Commission (CPUC) both use the IEPR load forecast to develop their respective annual transmission plan and resource portfolios. It is concerning that PG&E presented three projects for approval[14] based on expected load increases in PG&E’s service area that are not consistent with California Energy Commission (CEC) most recent load forecasts and CAISO findings..[15],[16]
D. PTOs should conduct Grid Enhancing Technology pilots to Determine Best Practices for Implementing These Cost-Saving Devices.
- Advanced Conductors Pilots
Cal Advocates requests that PG&E and San Diego Gas & Electric Company (SDG&E) consider advanced conductor pilots to assist with determining the best practice for implementing this cost saving technology in their service area. Advanced Conductors have a power carrying capacity that is approximately twice as much as traditional aluminum conductor steel-reinforced cable (ACSR) conductors.[17] CAISO Vice President Neil Millar explained in the February 15, 2024 Power Association of Northern California’s (PANC) monthly meeting that he believed that there would be more advanced conductor solutions presented in future Transmission Plans.[18] However, the CAISO’s draft 2023-2024 Transmission Plan does not recommend any projects with advanced conductors. The 2023-2024 plan recommends 26 projects for approval, amongst these, ten projects involve partial or full reconductoring of transmission lines. As reported in the CAISO’s April 9, 2024 stakeholder meeting, all ten of the proposed reconductoring projects will use traditional ACSR conductors. Meaning that none of the proposed projects will involve reconductoring with advanced conductors which is the most optimal way to cost-effectively increase transmission line capacity. [19]
So far, the only reconductoring project CAISO has approved with advanced conductors is the Southern California Edison Company (SCE) Lugo-Victor 230 kV Reconductoring project.[20], [21] SCE also uses advanced conductors to address clearance issues in its capital maintenance program according to Neil Millar.[22] Thus, SCE seems to have adopted advanced conductors as a tool to address line issues, but the other PTOs have not.
- Power Flow Device Pilots
Cal Advocates also recommends that there be further investigation on the use of GETs to address immediate grid issues and to allow time for adequate study of mitigations and for mitigations to come online. Cal Advocates makes this request for two reasons. First, most of PG&E’s proposed projects in the 2023-2024 Draft Transmission Plan are needed by 2025 to address grid issues based on PG&E’s presented load need data.[23] Second, GETs generally take one to three years to deploy,[24] whereas on average, PG&E takes, five years or more to complete approved projects.[25] Since it is not likely that PG&E’s proposed projects will be implemented within the next two years,[26] interim solutions such as the installation of energy storage or other GETs should be considered and or piloted to address reliability issues effectively and in a timely fashion.
Power flow device technologies also continue to advance and are already an established lower-cost option to reconductoring. A 2016 PG&E power flow devices pilot determined that the costs of power flow devices could be 33% lower than reconductoring a section of a 230 kV line even when considering both construction and on-going operation and maintenance. [27] This pilot estimated that a proposed reconductoring solution would be $130 million whereas the power flow device technology solution would be $33 million.[28] Further, the Department of Energy finds that the power flow control devices have the potential to be more cost-effective solutions than traditional transmission buildout, saving millions of dollars in the short-term through project deferrals.[29]
E. PG&E Should Consider a French Camp Reinforcement Project Alternative
Consistent with prior comments,[30] Cal Advocates requests PG&E and CAISO consider a hybrid alternative for the French Camp reinforcement project with a 15-megwatt (MW) energy storage unit and reconductoring Weber-French Camp #2 60 kV line with advanced conductors. This alternative may be just as effective as the proposed option but would have a lower cost.
[1] Cal. Pub. Util. Code, § 309.5.
[2] CAISO 2023-2024 Transmission Plan, April 1, 2023 at p. 43.
[3] CAISO Transmission Planning Process Draft 2023-2024 Transmission Plan, April 1, 2024 at p. 43.
[4] PG&E 2023 Final Per Unit Cost Guide, September 18, 2023.
[5] CAISO Transmission Planning Process Draft 2023-2024 Transmission Plan, April 1, 2024 at pp. 45, 46, 56, & 57.
[6] PG&E 2023 Final Per Unit Cost Guide, September 18, 2023. Located here: California ISO - Participating transmission owner per unit costs - 2023 (caiso.com)
[7] CAISO Transmission Planning Process Draft 2023-2024 Transmission Plan, April 1, 2024 at pp. 51, 52, 53, & 55.
[8] CAISO Transmission Planning Process Draft 2023-2024 Transmission Plan, April 1, 2024 at pp. 47 & 48.
[9] PG&E’s 2023 Request Window Proposal CAISO 2023-2024 Transmission Planning Process, September 27, 2023 at pp. 29,48, & 71.
[10] California’s Progress in Advancing Transmission Planning and Permitting, Center for Energy Efficiency and Renewable Technology and GridLab, report 2023 at p. 12.
[11] PG&E’s 2023 Request Window Proposal CAISO 2023-2024 Transmission Planning Process, September 22, 2023 at pp. 7, 12, 17, 24, 26, 27, 28, 40, 46, 60, 65 & 70.
[12] United States Department of Energy. Dynamic Line Ratings: Report to Congress. June 2019.
[13] United States Department of Energy. Next-Generation Grid Technologies. November 2021.
[14] The PG&E projects that were presented to address higher load projections than the CEC are the French Camp, Spence 60 kV Area, and Tejon Area Reinforcement projects.
[15] CAISO Reliability Assessment and Study Updates (Presentation), November 16, 2023 at p. 10.
[16] PG&E’s 2023 Request Window Proposal CAISO 2023-2024 Transmission Planning Process, September 27, 2023 at pp 31 and p. 72 and stakeholder meeting discussion on September 27, 2023.
[17] Accelerating Transmission Expansion by Using Advance Conductors in Existing Right-of-wat, Energy Institute at the Hass Business School at University of California, Berkeley, February 2024, at p. 4.
[18] February 15, 2024 Power Association of Northern California Virtual Monthly meeting at 45:48-46:32 February 15 Virtual Monthly Meeting - Zoom
[19] 2035 and Beyond the Report, Reconductoring with advance conductors can accelerate the rapid transmission expansion required for a clean grid, GridLab, p. 26.
[20] ISO-Board-Approved-2022-2023-Transmission-Plan.pdf (caiso.com)
[21] Proposed SCE Submittal into the 2022-2023 Transmission Planning Process, 2022-2023 CAISO TPP, September 28, 22 at p. 14 SCE refers to advance conductors as High Temperature Low Sag (HTLS) conductors.
[22] February 15, 2024 Power Association of Northern California Virtual Monthly meeting at 45:04-45:30 February 15 Virtual Monthly Meeting - Zoom
[23] PG&E’s 2023 Request Window Proposal CAISO 2023-2024 Transmission Planning Process, September 27, 2023 at pp 16, 22, 32, 45, 58 & 68.
[24] Pathways to Commercial Liftoff: Innovative Grid Deployment, U.S. Department of Energy, April 2024 at p. 21.
[25] PG&E has a large existing backlog of CAISO-approved projects most of which are considerably delayed. As noted in the January 2024 CAISO Transmission Development Forum workbook, PG&E has a total of 95 CAISO TPP-approved transmission projects that are pending operational status to date. Of these, 24 projects were approved before the 2013-14 Transmission Plan, over 10 years ago. One of PG&E’s severely delayed projects, the Metcalf-Piercy & Swift and Newark-Dixon Landing 115 kV Upgrade, was approved by CAISO 20 years ago, in 2003.
[26] PG&E has a large existing backlog of CAISO-approved projects most of which are considerably delayed. As noted in the January 2024 CAISO Transmission Development Forum workbook, PG&E has a total of 93 CAISO TPP-approved transmission projects that are pending operational status to date. Of these, 24 were approved before the 2013-14 Transmission Plan, over 10 years ago. One of PG&E’s severely delayed projects, the Metcalf-Piercy & Swift and Newark-Dixon Landing 115 kV Upgrade, was approved by CAISO 20 years ago, in 2003.
[27]Power flow control devices are a class of many technologies and methods. Members of this class include active and passive devices (such as power electronic controllers or passive distributed series reactors) along with operational schemes such as removing a line from operation in order to force flow onto adjacent higher capacity lines. The mentioned study piloted a distributed series reactor.
[28] PG&E EPIC 1.09C -Test New Remote Monitoring and Control Systems for T&D Assets, Discrete Series Reactors, December 29, 2026, p. 4.
[29] Source: U.S. Department of Energy. Next-Generation Grid Technologies at pp. 24-25. Available at: https://www.energy.gov/oe/articles/next-generation-grid-technologies-report-download?utm_medium=email&utm_source=govdelivery.
[30] Cal Advocates Comments on September 26-27, 2023 2023-2024 Transmission Planning Process, October 11, 2023 at p. 5.
4.
Please provide your organization’s comments on Policy-driven Projects Recommended for Approval.
Cal Advocates’ comments regarding transmission investments needed to bring Offshore Wind (OSW) onto the California grid are as follows:
- Alternative Call Areas: CAISO has stated that Alternative E of the Interconnection to Humboldt 115 kV System will "Ensure transmission will not be stranded in the event that offshore wind does not get developed as quickly as anticipated or if it shifts to a different call area."[1] CAISO appears to acknowledge the California Public Utilities Commission’s (CPUC’s) Integrated Resource Planning (IRP) portfolio resources while also anticipating that the OSW projects might need an "offramp" if the details of integrating Californian OSW change. Cal Advocates requests that CAISO provide some details on how these transmission assets would not be stranded if the location of OSW changes. CAISO should have a public plan in place for the specific proposed projects in Alternative E, in the event that the projects will not be used for the specific Humboldt wind call areas.
- Line Routing Analysis: For the New Humboldt 500 kV substation, with a 260-mile High Voltage Direct Current (HVDC) line to the Collinsville station, Cal Advocates is concerned that there is no analysis of the feasibility of the proposed line routing. CAISO stated during the TPP Stakeholder meeting on April 9, 2024 that the routing would become clear during the competitive bidding process. However, ensuring that the proposed project is realistic before going to competitive bidding could streamline the bidding and proposal process, and prevent possible redundant line routing analysis. For this reason, Cal Advocates requests CAISO to complete a rudimentary line routing analysis.
- Project Phasing: Cal Advocates also encourages phasing OSW development, and focusing development efforts in succession, rather than in parallel. This would maximize lessons learned for constructing transmission lines from the call area to land and allow CAISO and the PTOs to apply these lessons learned to subsequent OSW projects. Developing OSW in multiple call areas is important to reach California's climate change goals, but in the absence of any active floating OSW pilots in California, it would benefit the state to be deliberate about how and when it proceeds with transmission projects to bring floating OSW power to interconnection points on land.
- Explore other line uses: It is possible that the proposed new transmission lines could be useful for moving power from the California-Oregon Intertie to load centers. For this reason, Cal Advocates requests further study of the potential additional line activity once the proposed OSW lines are in place.
- Consider Alternative Financing to Manage the Ratepayer Impacts of Proposed OSW Transmission Investments.
Given the significant costs and risks associated with new transmission line development, Cal Advocates supports the exploration of alternative financing for the proposed OSW investments. Alternative financing, in contrast to traditional transmission access charge cost recovery, could potentially reduce the total cost burden on ratepayers as well as assist with phasing in project debt over a greater time period. The CEC laid out a few alternative financing options in its 2023 Integrated Energy Policy Report. These options include exploring options for federal funds, issuing new bonds, allocation of funds from existing credit trading or the General Fund, or expansion of existing financing mechanisms such as the Climate Catalyst Fund at the California Infrastructure and Economic Development Bank.[2] Cal Advocates supports greater exploration of these options amongst the relevant state agencies since bonds financing for OSW transmission would result in collecting project funds not just from ratepayers and public financing for OSW would lower the total financing costs for the proposed investments.
- Cal Advocates also requests CAISO and NorthernGrid to explore options to jointly develop OSW transmission.
Both California and Oregon are pursuing OSW development in close proximity to each other at Humboldt and Brookings, respectively. Due to the proximity of these OSW development areas, the Environmental Defense Fund suggested that there is an opportunity for CAISO and NorthernGrid to jointly develop transmission to integrate OSW in Northern California and Oregon into the bulk high-voltage system.[3] Cal Advocates supports this approach since jointly owned transmission facilities can spread the cost and responsibility for owning and maintaining a transmission facility more broadly and, as a result, reduce the total project cost for California ratepayers. The Federal Energy Regulatory Commission (FERC) has also encouraged joint partnerships for interregional transmission projects to mitigate financing and siting risks associated with transmission projects.[4] Further, FERC states that “given the nature of a joint-ownership arrangement, individual parties working together may achieve efficiencies in addressing their collective transmission needs and, therefore, achieve lower overall costs compared to developing transmission facilities to resolve more individualized needs in a more piecemeal manner.”[5]
For reference, the following are examples of successful jointly owned transmission in the west:
- The Pacific Direct Current Intertie (PDCI) is an 841-mile 500 kilovolt (kV) transmission line from northern Oregon to southern California. Bonneville Power Administration, Los Angeles Department of Water and Power, Southern California Edison Company and the Cities of Burbank, Glendale and Pasadena jointly built, own, and operate this line.[6]
- The Mead-Phoenix is a 256-mile 500 kV transmission line that extends from Phoenix, Arizona to the southwest of Boulder City, Nevada. Western Area Power Administration, Salt River Project, Southern California Public Power Authority, and the Cities of Modesto, Santa Clara and Redding jointly constructed and now operate and maintain this line.[7]
- Cal Advocate also suggests the state agencies explore establishing a transmission authority to attract public-private partnerships and secure alternative financing for OSW development and other significant transmission investments needed to meet the state’s clean energy targets.
Both New Mexico and Colorado established transmission authorities to assist with new transmission developments in their states. These transmission authorities are the New Mexico Renewable Energy Transmission Authority and the Colorado Electric Transmission Authority, respectively. Both entities can issue and sell bonds to finance projects and enter into agreements with private developers to jointly develop new transmission. These entities also assist with planning and permitting new transmission development.[8]
The following are examples of projects in California that were developed by Joint Power Authorities in the west.
- The California-Oregon Transmission Project (COTP), which is a 340-mile 500 kV transmission line between the California-Oregon border and Central California. The Transmission Agency of Northern California (TANC) planned, designed, and constructed this line for its members. These members include the cities of Alameda, Biggs, Gridley, Healdsburg, Lodi, Lompoc, Palo Alto, Redding, Roseville, Santa Clara, and Ukiah as well as the Sacramento Municipal Utility District, the Modesto Irrigation District, and the Turlock Irrigation District. The Plumas-Sierra Rural Electric Cooperative is an Associate Member.[9] TANC now owns about 87 percent of the project, and is the project manager, coordinating the use of COTP facilities among project participants. Other participants in COTP are Western Area Power Administration, PG&E, City of Redding, and the Carmichael Water District.[10]
- The Southern Transmission System, which is a 488-mile 500kV transmission line extending between the Intermountain Power Project and the Adelanto Switching Station. The Los Angeles Department of Water and Power operates and maintains the line.[11] Southern California Public Power Authority joint planned, financed, constructed this transmission line for the Cities of Anaheim, Burbank, Glendale, Los Angeles, Pasadena, and Riverside.[12]
[1] Draft 2023-2024 Transmission Plan, CAISO, April 1, 2024, P. 70.
[2] Adopted 2023 Integrated Energy Policy Report with Errata, California Energy Commission, February 14, 2024 at pp. 7 and 48-49.
[3] Energy Defense Fund Comments on Draft 2022-2023 Transmission Plan, Michael Colvin, April 11, 2023 at p.6.
[4] Promoting Transmission Inv. Through Pricing Reform, Policy Statement, 77 FR 69754 (Nov. 21, 2012), 141 FERC ¶ 61,129 (2012)) at p. 18.
[5] Building for the Future Through Electric Regional Transmission Planning and Cost Allocation and Generator Interconnection, Docket No. RM21-17-000, April 21, 2022, 197 FERC, 61,028 at pp. 294-295.
[6] City of Los Angeles Resolution 018007, July 18, 2017 at p. 1.
[7] Federal Register Vol. 55 No. 174, September 7, 1990 at p. 1.
[8] California’s Progress in Advancing Transmission Planning and Permitting, A 2023 Review, GridLab and CEERT, at pp. 25-26.
[9] About TANC
[10] Joint Ownership of Transmission, American Public Power Association, February 2009 at p. 8.
[11] City Of Anaheim Application for Participating Transmission Owner Status, July 31, 2002 at p. 3.
[12] SCPPA | Southern Transmission System Project
5.
Please provide your organization’s comments on the Economic Assessment.
Cal Advocates supports CAISO’s recommendation to continue studying the costs and benefits as well as the need for the proposed new 500 kilovolt (kV) line between the Lugo and Trout Canyon substations referred to as the Trout-Canyon Lugo line.[1] CAISO put the Trout-Canyon Lugo line on-hold in the 2022-2023 TPP cycle to allow for an alternative analysis with the Mead – Adelanto Project Upgrade (MAP) Upgrade project. For reference, the MAP Upgrade has a cost estimate of $1.5 billion[2] and the Trout-Canyon Lugo line had an estimated cost between $1.5 to $2 billion in 2022, but its costs are now estimated at $2 billion.[3] The 2023-2024 TPP analysis determined that neither project has a benefit-to-cost ratio greater than one.[4] However, only the MAP Upgrade project addressed congestion on Path 61 and the Lugo to Victorville 500 kV line.[5]
Regarding the policy need for the Trout-Canyon Lugo line project, as CAISO Vice President Neil Millar explained in the February 15, 2024 PANC monthly meeting, the results from the 2023-2024 Transmission Plan study do not support moving forward with the Trout-Canyon Lugo line as a policy project at this time. However, Vice President Millar predicts that the study results for the 2024-2025 TPP cycle will demonstrate a need for the Trout-Canyon Lugo project based on CPUC’s final resource portfolios for study in the 2024-2025 TPP cycle.[6]
For this reason, Cal Advocates requests that CAISO continue to evaluate the MAP Upgrade project as an alternative to the Trout-Canyon Lugo line to meet the state’s policy needs for two reasons: (1) the MAP Upgrade project can mitigate congestion on Path 61 as well as the Lugo to Victorville 500 kV line unlike the Trout-Canyon line, and (2) the MAP Upgrade project involves increasing the capacity of an existing line and is less risky than the Trout-Canyon Lugo line. In contrast, the Trout Canyon Lugo line involves establishing a new high voltage corridor and building a new high voltage line. Most new transmission corridors face opposition for aesthetic and environmental concerns from the public and, for this reason, the Trout-Canyon Lugo line is likely to have more cost increases.[7], [8]
[1] The Trout-Canyon Lugo Line project was proposed to meet a policy need in the 2022-2023 TPP cycle to access renewables in the Gridliance West/Valley Electric Association area.
[2] CAISO Transmission Planning Process Overview Draft 2023-2024 Transmission Plan, (presentation) April 9, 2024 at p. 106.
[3] The Trout-Canyon Lugo 500 kV line cost estimate was $1.5 to $2 billion in the May 18, 2023 CAISO 2022-2022 Transmission plan at p. 82. The project cost estimate in the 2023-2024 TPP cycle is $2 billion.
[4] CAISO Transmission Planning Process Overview Draft 2023-2024 Transmission Plan, (presentation) April 9, 2024 at p. 106.
[5] CAISO Transmission Planning Process Overview Draft 2023-2024 Transmission Plan, (presentation) April 9, 2024 at p. 105
[6] February 15, 2024 Power Association of Northern California Virtual Monthly meeting at 41:30-42:50.
[7] The Trout-Canyon Lugo 500 kV line cost estimate was $1.5 to $2 billion in the May 18, 2023 CAISO 2022-2022 Transmission plan at p. 82. The project cost estimate in the 2023-2024 TPP cycle is $2 billion.
[8] California’s Path to Decarbonization, Transmission Planning Permitting and Timely Construction, Gridlab and Center for Energy Efficiency and Renewable Technology, July 2023 at p. 35.