Bay Area Municipal Transmission Group (BAMx)
Submitted 12/04/2023, 10:34 am
Submitted on behalf of
City of Palo Alto Utilities and Silicon Valley Power (City of Santa Clara)
1.
Please provide your organization’s comments on the Recommended Reliability Projects less than $50 million for the North Region.
The Bay Area Municipal Transmission group (BAMx)[1] appreciates the opportunity to comment on the CAISO's 2023-2024 Transmission Planning Process. The comments and questions below address the material presented at the CAISO Stakeholder meeting on November 16, 2023.
BAMx has no comments on the recommended reliability projects less than $50 million for the North region at this time. However, as the CAISO has indicated in its response[2] to BAMx comments, it is currently reviewing the need and timing for some of the proposed transmission projects. These projects include the Crazy Horse Canyon-Salinas-Soledad #1 and #2 115 kV Line Reconductoring, Camden 70 kV Reinforcement Project, Reedley 70 kV Capacity Increase Project, Vaca Dixon Reinforcement (Rescope), and Diablo Canyon High voltage mitigation. We request the CAISO to take BAMx’s comments on these projects into consideration as it evaluates these projects.
[1] BAMx consists of City of Palo Alto Utilities and City of Santa Clara, Silicon Valley Power.
[2] CAISO Response Matrix to Stakeholder Comments, 2023-2024 Transmission Planning Process Stakeholder Meeting, September 26-27, 2023.
2.
Please provide your organization’s comments on the Recommended Reliability Projects less than $50 million for the South Region.
No comments at this time.
3.
Please provide your organization’s comments on the MIC Expansion Requests.
No comments at this time.
4.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the SCE & GLW areas.
Need for a Method to Reevaluate Need for the Approved Transmission Projects When Assumed Condition Change
In the Draft 2022-2023 Transmission Plan, the CAISO considered the approval of the Trout Canyon-Lugo 500 kV Line with an estimated capital cost of $2 billion.[1] However, its approval was held back in the Final Transmission Plan due to a letter from Lotus Infrastructure Partners on April 25, 2023,[2] which identified an alternative solution, causing the CAISO additional time to assess.[3] If this alternative had not been proposed at the end of the 2022-2023 TPP cycle, the CAISO probably would have approved the Trout Canyon-Lugo 500 kV line as one of the policy-driven transmission projects in the Final Transmission Plan. It is the CAISO’s standard practice to model all the previously-approved projects in the starting power flow cases that are used in a given transmission planning cycle.[4] So, had the CAISO approved the Trout Canyon-Lugo 500 kV line in the 2022-2023 Transmission Plan, it would have been modeled in the 2023-2024 TPP cases as given. Therefore, the continued need for the Trout Canyon-Lugo 500 kV line would not have been evaluated in the 2023-2024 TPP. And there would be no need for a superior alternative.
Since the Trout Canyon-Lugo 500 kV line was not approved in the 2022-2023 TPP, the CAISO is evaluating whether that project is the most effective mitigation solution in the current TPP. During the November 16th stakeholder meeting, the CAISO, while presenting the preliminary policy assessment for the East of Pisgah Interconnection area, indicated that they are evaluating the need for solutions to address some deliverability constraints. However, the Trout Canyon-Lugo 500 kV line project may or may not be the solution that would be needed to address those deliverability constraints. These preliminary findings indicate that a combination of the change in the resource portfolios, especially in the VEA area and the Southern Area Reinforcement projects[5] approved in the 2022-2023 Transmission Plan, has reduced or eliminated the need for a major project like the new Trout Canyon-Lugo 500 kV line.
BAMx believes this is an example of the need to reexamine the appropriateness of projects, even if they have been previously approved. BAMx has been asking the CAISO to be open to such a reevaluation for many years. A good example of the benefits of such re-examination was when the need for previously approved PG&E projects was reevaluated in 2016-2018. CAISO’s effort resulted in over $3 billion of project cancellations and scope reductions. BAMx requests the CAISO develop a stakeholder process to define a set of circumstances when such reevaluation would occur. We understand that there would be limitations to such a reevaluation process. Project cost could be one such criterion. Of course, regulatory issues like PTO recovery of costs for an abandoned project would need to be considered. But ratepayer costs to reimburse for early feasibility work would be more than offset by not having to build a project or selecting a better alternative with the latest information on the need for projects. A less desirable alternative to a separate process may be to allow additional time to investigate the above proposal during the development of a plan for the next planning cycles. If this vehicle is chosen, multiple stakeholder meetings should be scheduled.
Regarding the Trout Canyon-Lugo 500 kV line project, BAMx, therefore, recommends that the CAISO deploy the following approach in its determination of the transmission need. Check whether the other transmission projects (e.g., the Southern Area Reinforcement projects in 2022-2023 TPP under consideration for approval lower or eliminate the need for a given project (e.g., Trout Canyon-Lugo 500 kV line project). This analysis will require the CAISO to model a case with and without the Trout Canyon-Lugo 500 kV line project, assuming that the Southern Area Reinforcement projects are online to verify whether the Trout Canyon-Lugo 500 kV line is genuinely needed to address certain deliverability constraints. A similar approach should be implemented to confirm the need for all previously approved projects. If limited bandwidth to review and confirm the need for all previously-approved transmission projects in every planning cycle is a constraint, then the CAISO needs to develop criteria to select a transmission project for reevaluation in consultation with the stakeholders.
[1] CAISO Draft 2022-2023 Transmission Plan, p. 6 & 133, April 3, 2023.
[2] http://www.caiso.com/InitiativeDocuments/Letter-Alternative-to-Trout-Canyon-Lugo-500-kV-line-Apr242023.pdf
[3] CAISO Final 2022-2023 Transmission Plan, p. 82, May 10, 2023.
[4] CAISO 2023-2024 Transmission Study Plan, p.14.
[5] That is, the Imperial Valley– North of SONGS 500 kV Line and Substation, North of SONGS–Serrano 500 kV Line, and Serrano–Del Amo–Mesa 500 kV Transmission Reinforcement projects.
5.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the SDG&E area
No comments at this time.
6.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the PG&E area.
Anticipated Significant Changes to Offshore Wind Resource Selection Requires Revisiting Current TPP Portfolios and CAISO’s Determination Regarding Policy-Driven Transmission Upgrades
BAMx appreciates that the CAISO is evaluating the resource portfolios that were provided by the California Public Utilities Commission (CPUC) in March 2023 to be utilized in its 2023-2024 TPP.
The latest CPUC IRP Ruling on the 2023 Preferred System Plan recommends the 25 MMT Core portfolio as the Base portfolio.[1] If it is adopted by the Commission, then it would be transmitted to the CAISO as both the reliability and policy-driven base case scenario to be analyzed by the CAISO in the 2024-2025 TPP. As summarized in Table 1 below, the Base portfolio in the 2023-2024 TPP included 1,607 MW of offshore wind (OSW) resources in the North Coast area, whereas the Sensitivity portfolio in the same TPP cycle assumed as high as 8,045 MW of OSW. The expected costs of offshore wind are now significantly higher relative to its competing resources across the modeling horizon based on the most recent 2023 National Renewable Energy Laboratory (NREL) Annual Technology Baseline (ATB).[2] As a result, the proposed Base portfolio and the Sensitivity portfolio in the latest Draft Base portfolio select no OSW resources in the North Coast. Also, the proposed Base portfolio in the latest Draft Base portfolio includes only 4,531 MW of OSW, which is entirely mapped in the Morro Bay Call area (Central Coast). In contrast, the proposed Sensitivity scenario does not select a single MW of OSW. As evident from Table 1 below, the proposed 2024-2025 TPP portfolios constitute a significant departure from the past portfolios that require serious consideration in the CAISO’s current, i.e., the 2023-2024 TPP cycle.
Table 1: A Comparison of Offshore Wind Resource Capacity (MW) Selected in the 2022-2023 TPP vs. 2023-2024 TPP vs. Draft 2024-2025 TPP Portfolios.
Offshore Wind Area
|
2022-2023 TPP*
|
2023-2024 TPP**
|
Draft 2024-2025 TPP***
|
Base Portfolio
|
Sensitivity Portfolio
|
Base Portfolio
|
Sensitivity Portfolio
|
Base Portfolio
|
Sensitivity Portfolio
|
Morro Bay Call Area
|
1,588
|
3,100
|
3,100
|
5,355
|
4,531
|
0
|
Humboldt Call Area
|
120
|
1,607
|
1,607
|
2,600
|
0
|
0
|
Del Norte Area
|
0
|
0
|
0
|
3,445
|
0
|
0
|
Cape Mendocino Area
|
0
|
0
|
0
|
2,000
|
0
|
0
|
Total North Coast
|
120
|
1,607
|
1,607
|
8,045
|
0
|
0
|
Total
|
1,708
|
4,707
|
4,707
|
13,400
|
4,531
|
0
|
* https://stakeholdercenter.caiso.com/RecurringStakeholder Processes/2022-2023-Transmission-planning-process
** https://stakeholdercenter.caiso.com/RecurringStakeholder Processes/2023-2024-Transmission-planning-process
*** CPUC ED, “2023 Proposed PSP & 2024-2025 TPP Resolve Modeling Results,” October 5, 2023
BAMx agrees with the CAISO that they cannot make any assessment on the draft 2024-2025 TPP portfolios until they are finalized and provided to them by the CPUC as part of the Final Decision in the IRP proceeding. However, as the CAISO is considering approval of transmission project(s) that are found needed to meet the OSW resource needs of the Base portfolio, it needs to be cognizant of the changed circumstances regarding the economic viability of OSW resources in the North Coast. If the CAISO approves a policy-driven project to accommodate the OSW resources in the North Coast, that could not only prove to be a sub-optimal outcome but could also lead to stranded asset(s) based on the current expectations regarding the cost of OSW as reflected in the draft 2024-2025 TPP portfolios. BAMx urges the CAISO to delay the approval of any policy-driven transmission related to accessing OSW in the North Coast until the CPUC provides clarity based on the above-described updated information.
This provides another example that would benefit from the above proposal to set up criteria for reevaluation of previously approved projects. If the CAISO does approve some OSW-related transmission projects despite knowing there is a likelihood that 2024-2025 TPP portfolios would no longer require proposed projects, the CAISO could reevaluate its earlier decision. Some development costs would have been spent unnecessarily, but they would be minor compared to building a project that well-exceeds the need.
Need Cost Estimates of Major Transmission Options to Access OSW in North Coast and Additional Transmission Upgrades Triggered By Procurement of Humboldt/North Coast OSW
During the November 17th call, the CAISO verbally provided the high-level cost estimates for the following three transmission options.
- 500 kV AC line to Fern Road;
- Onshore overhead VSC-HVDC to Collinsville Substation; and
- Offshore sea cable VSC-HVDC to a Substation in the Bay Area.
BAMx understands that the CAISO will consider the combined capital cost of these major transmission options and the additional transmission reinforcements that would be needed for each of the three options to select the most economic transmission option in the current transmission planning cycle. BAMx supports the CAISO approach but reminds CAISO that without the CAISO providing the capital cost estimates for each of the transmission enforcements, it would be impossible for the stakeholders to weigh in on the cost-effectiveness of the three transmission options. BAMx understands that the CAISO plans to provide all the capital cost estimates in its Draft Transmission Plan. However, having preliminary capital cost estimates at such a late stage in the TPP cycle, provides stakeholders with very little time to provide meaningful feedback and for CAISO to incorporate it in the Final Transmission Plan. We, therefore, urge the CAISO to post the capital cost estimates of all transmission projects under consideration as they become available at the CAISO’s secured transmission planning web portal.
Further Technical Evaluation of OSW Transmission Projects Needs to Be Accompanied By High-Level Permitting/Feasibility/Environmental Assessment
Integrating North Coast OSW is a challenging objective with technical, environmental, and scheduling risks. Such risks suggest value in staging transmission improvements in a manner where decisions on higher cost and technically challenging elements are made later in the process once better information is available. The choice between the terrestrial alternatives (Fern Road or Collinsville) will likely depend on environmental factors. It does not appear that these environmental and permitting constraints have been considered in the determination of transmission options yet. Similarly, the CAISO needs to perform high-level technical feasibility and supply chain issues associated with the submarine cable option(s). CAISO’s approval of any green-field policy-driven transmission project without considering the feasibility challenges and environmental permitting constraints for transmission development would be counter-productive. Therefore, BAMx recommends that the CAISO conduct a high-level feasibility and environmental permitting assessment before recommending any particular transmission project to access North Coast OSW.
Questions on Potential Mitigation Projects for Humboldt Area Offshore Wind Interconnection
- Please explain why the Contra Costa - Lone Tree Series compensation project helps address the P1 overload on the North Dublin - Vineyard 230 kV under the Base B alternative instead of reconductoring that line.[3]
- It appears that Lone Tree – Cayetano – Newark Corridor Series Compensation approved in 2022-2023 Transmission is not adequate in addressing the deliverability issues in the Base A alternative.[4] Please evaluate why the reconductoring of the Cayetano - Lone Tree (USWP-Cayetano) 230 kV line is preferred over revising the scope of the Lone Tree – Cayetano – Newark Corridor Series Compensation project.
- Please explore the effectiveness and adequacy of a series compensation project as a mitigation measure for the Tesla - Newark 230 kV constraint in lieu of reconductoring the line in the Base B and Base C alternatives.[5]
[1] Administrative Law Judge’s Ruling (“Ruling”) on the 2023 Preferred System Plan (PSP) and portfolio to be sent to the CAISO for analysis in its 2024-2025 TPP, Ruling, p. 36, October 5, 2023.
[2] CPUC ED, “2023 Proposed PSP & 2024-2025 TPP Resolve Modeling Results,” October 5, 2023, Slide #13.
[3] See the “PG&E Humboldt Area Offshore Wind Interconnection Alternatives Related Results,” Policy-driven Deliverability Assessment Preliminary Results, 2023-2024 TPP Stakeholder Meeting, November 16, 2023, pp. 101, 109 and 119.
[4] See the “PG&E Humboldt Area Offshore Wind Interconnection Alternatives Related Results,” Policy-driven Deliverability Assessment Preliminary Results, 2023-2024 TPP Stakeholder Meeting, November 16, 2023, pp. 101, 110 and 119.
[5] See the “PG&E Humboldt Area Offshore Wind Interconnection Alternatives Related Results,” Policy-driven Deliverability Assessment Preliminary Results, 2023-2024 TPP Stakeholder Meeting, November 16, 2023, pp. 101, 111 and 119.
7.
Please provide your organization’s comments on the Preliminary Economic Analysis Results.
In the 2022-2023 TPP, the CAISO identified the benefits of the projects approved in the 2021-2022 Transmission Plan in terms of reduced renewable curtailments, such as the GridLiance/VEA 230 kV upgrades, Manning, Collinsville, Moss Landing - Las Aguilas projects.[1] However, no such benefits were attributed to any transmission projects approved in the last (2022-2023) Transmission plan, such as the Lugo – Victor – Kramer 230 kV Upgrade or the Southern Area Reinforcement projects during the November 16th stakeholder meeting. Does that mean no such benefits were observed as part of the preliminary economic analysis, or were they not reported? Please explain. BAMx also requests the CAISO to calculate the production cost benefits for all the policy-driven projects under consideration for approval, just the way the CAISO had done for the Manning and Collinsville projects in the 2021-2022 Transmission Plan.[2]
[1] Preliminary Economic Assessment Results, 2022-2023 Transmission Planning Process Stakeholder Meeting November 17, 2022, p. 19.
[2] CAISO 2021-2022 Transmission Plan March 17, 2022, pp. 300-301.
8.
Please provide any additional comments on the November 16, 2023 Transmission Planning Process Stakeholder Meeting.
BAMx appreciates the opportunity to comment on the 2023-2024 Transmission Plan preliminary Policy and Economic assessment results and acknowledges the significant effort of the CAISO staff in developing this material.
California Public Utilities Commission - Public Advocates Office
Submitted 12/04/2023, 05:25 pm
1.
Please provide your organization’s comments on the Recommended Reliability Projects less than $50 million for the North Region.
The Public Advocates Office at the California Public Utilities Commission (Cal Advocates) provides these comments on the transmission project recommendations presented at the 2023-2024 Transmission Planning Process Stakeholder meeting on November 16, 2023. Cal Advocates is an independent ratepayer advocate with a mandate to obtain the lowest possible rates for utility services, consistent with reliable and safe service levels and the state’s environmental goals.[1]
[1] Cal. Pub. Util. Code, § 309.5.
2.
Please provide your organization’s comments on the Recommended Reliability Projects less than $50 million for the South Region.
Cal Advocates requests additional information to explain the proposed $40 million Etiwanda 230 kV Bus Short Circuit Duty (SCD) Mitigation project.[1] This proposed project involves only replacing twelve 230 kilovolt (kV) circuit breakers with an in-service date of 2027. Using Southern California Edison Company’s (SCE) 2023 Final Per Unit Cost Guide, Cal Advocates estimates the project should cost approximately $12.2 million. Cal Advocates arrived at this $12.2 million project cost estimate by referring to the unit cost for Circuit Breakers (without Transient Recovery Voltage Capacitors) and the costs for Transient Recovery Voltage (TRV) Capacitors for 230 kV Transmission Lines in SCE’s Unit Cost Guide.[2] We then multiplied this referenced Circuit Breaker costs at $916,000 by 12, which is the proposed number of replacement circuit breakers for the project, and the TRV Capacitor Costs at $212,000 by 4 because TRV Capacitors come in sets of three. We also applied the Escalation Factor of 1.0272 from SCE’s Unit Cost Guide for an in-service date of 2027.[3] Using this method, the project should cost approximately $12.2 million instead of $40 million. Since there is a $27.8 million difference between Cal Advocates’ cost estimate and the provided project cost estimate, Cal Advocates requests SCE explain the method it used to arrive at the $40 million cost estimate.
[1] 2023-2024 Transmission Planning Process SCE Eastern Area Less than $50 Million Projects Recommended for Approvals and Project for Concurrence, CAISO, November 16, 2023 at slide 24.
[2] SCE -2023- Final-Per-Unit-Cost-Guide, Cost Detail, Replacement Substation Equipment
[3] SCE -2023- Final-Per-Unit-Cost-Guide, Escalation Rates & Factors, Current SCE ESCALATION Rates
3.
Please provide your organization’s comments on the MIC Expansion Requests.
Cal Advocates appreciates CAISO’s transparency on California load serving entities’ Maximum Import Capacity (MIC) requests and has no other comment on this topic.
4.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the SCE & GLW areas.
Cal Advocates appreciates that CAISO considered protection schemes and energy storage as possible mitigation options to address deliverability issues with the preferred system portfolio in its analysis this TPP cycle.[1] Cal Advocates recommends CAISO also consider other grid enhancing technologies such as smart wires and increasing line or equipment ratings to address potential deliverability issues. These options would be more cost efficient for ratepayers than reconductoring and, for this reason, should be evaluated before reconductoring is considered as a possible mitigation option. The Federal Energy Regulatory Commission (FERC) also recommends that public utility transmission providers consider whether adding dynamic line ratings or advanced power flow control devices to existing transmission facilities could meet the same transmission need more efficiently or cost-effectively than a new transmission facility.[2]
[1] Policy-driven Deliverability Assessment Preliminary Results (Presentation), CAISO, November 16, 2023 (CAISO November 16, 2023 Presentation) at pp. 43-93.
[2] FERC Docket RM21-17-000, April 21, 2022, Item 274 at p. 217.
5.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the SDG&E area
Please refer to the comments provided in response to question number 4.
6.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the PG&E area.
Similar to our recommendations on SCE’s and Gridliance West’s (GLW) service areas, the proposed Pacific Gas and Electric Company (PG&E) area mitigations should first exhaust consideration of any protection schemes and grid enhancing technology (GET) mitigations options prior to considering new wire solutions. Cal Advocates supports CAISO’s inclusion of alternatives like reinstating 500 kV line rerates, as it is a cost-effective solution that addresses potential line overloads in the PG&E area. Once all economical mitigations have been exhausted, Cal Advocates supports consideration of new wire solutions that can be competitively bid.
Regarding Offshore Wind Study Results
Cal Advocates supports CAISO's approach to determining the most cost-effective option to integrate North Coast offshore wind (OSW), which involves investigating four base case options and four sensitivity options. Cal Advocates requests that CAISO provide cost estimates for the different integration options presented in the Transmission Planning Process (TPP) stakeholder meetings to allow for a stakeholder discussion on these cost estimates. Cal Advocates also requests discussion on whether investments to support exclusively North Coast OSW integration should be put on-hold in this TPP cycle. Cal Advocates makes this request because it appears that the Commission may not include North Coast OSW in its portfolio for study in the 2024-2025 TPP cycle based on preliminary busbar mapping results.[1]
If CAISO decides to support one of the proposed North Coast OSW integration options, Cal Advocates requests that this decision be presented in a TPP stakeholder meeting and not just included in the final plan without stakeholder discussion.
Proposed Projects to Bring North Coast OSW to Onshore Connections
As mentioned, in the presentation, CAISO did not provide project costs to integrate OSW to connection points onshore. Instead, CAISO referenced a 2023 Schatz Center Northern California and Southern Oregon Offshore Wind Transmission Study for cost estimates. This report explains that the most expensive option amongst the upgrades considered is “the utilization of HVDC subsea cables, estimated at $4.0 billion. In comparison, the overland routes to Fern Road substation are estimated at $2.4 billion, while HVDC injections to Collinsville substation are estimated at $2.1 billion.”[2]
If the amount of North Coast OSW is increased from the base case amount at 1,607 MW to 8,045 MW, as proposed in the sensitivity case, Cal Advocates assumes that the integration costs would increase.[3] To confirm this cost increase, Cal Advocates request CAISO provide a cost estimate to integrate the proposed amount of North Coast OSW in the sensitivity case.
Possible Financial Impact of Bringing North Coast OSW from Onshore Connections to Load
At the November 16, 2023 stakeholder meeting, CAISO also presented 10 additional mitigations necessary to bring North Coast OSW to load. Cal Advocates’ interpretation of the CAISO’s tariff suggests the following three projects would be competitively bid, to support primarily North Coast offshore wind:[4], [5]
- New Fern Road-Tesla 500 kV Line;
- Collinsville 230 kV Reactor; and
- New Eastshore 230/115 transformer Bank #3.
Competitively bidding projects would reduce the capital costs associated with reaching California’s energy policy goal and presents a cost saving opportunity for ratepayers.
It is worth noting that CAISO’s November 16, 2023 presentation did not highlight the potential transmission investments needed to integrate Morro Bay OSW. The policy portfolio for study in this 2023-2024 TPP cycle includes 3,100 MW of Morro Bay OSW for the base case and 5,355 MW for the sensitivity. For this reason, Cal Advocates requests CAISO confirm the transmission investments needed to integrate the proposed amount of Morro Bay OSW. Based on the November 16, 2023 presentation, its seems that only a transformer at Wheeler Ridge 115/70 kV Transformer #2 would be needed for the base case.[6]
Financial Impact of OSW Transmission Mitigations
The mentioned 2023 California and Oregon OSW study estimates that California’s total cost for land-based and undersea infrastructure costs to support OSW integration from $5.13 billion to $12.33 billion.[7] Cal Advocates requests CAISO present these cost estimates in the next TPP meeting for further discussion to clarify the OSW locations and projects considered in this cost estimate. This discussion should cover the anticipated OSW transmission costs with the current base and sensitivity system portfolios for study in CAISO’s 2024-2025 TPP cycle.
[1] CPUC Energy Division, Integrated Resource Planning (IRP) Proposed Portfolios for the 24-25 Transmission Planning Process (TPP) and Preliminary Busbar Mapping, October 20, 2023, at 30. Available at https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/integrated-resource-plan-and-long-term-procurement-plan-irp-ltpp/2023-irp-cycle-events-and-materials/tpp-psp_10-20-23_workshop_tppbusbarslides.pdf.
[2] Northern California and Southern Oregon Offshore Wind Transmission Study, Schatz Energy Research Center, NREL, et al, October 2023 at p. 19.
[3] CAISO November 16, 2023 Presentation at p. 35.
[4] CAISO November 16, 2023 Presentation at p. 125, the portfolio considered is 2,895 MW which includes 1,607 MW of offshore wind.
[5] CAISO November 16, 2023 Presentation at p. 108, the portfolio MW behind the PittsburgF 230 kV constraint is 1,682 MW not 1,607 MW, so the proposed Collinsville 230 kV Reactor would support the delivery of OSW and some additional base case portfolio resources.
[6] CAISO November 16, 2023 Presentation at p. 154.
[7] Northern California and Southern Oregon Offshore Wind Transmission Study, Schatz Energy Research Center, NREL, et al, October 2023 at p. 6.
7.
Please provide your organization’s comments on the Preliminary Economic Analysis Results.
To address the observed congestion in the Southern California Edison East of Pisgah and Lugo to Victorville area, CAISO identifies the Trout Canyon to Lugo 500 kV line as a possible mitigation.[1] Cal Advocates requests CAISO provide two additional pieces of information with its Trout Canyon – Lugo 500 kV line analysis.
First, CAISO should provide information that illustrates the policy and economic benefits from the Southern Reinforcement projects approved in the 2022-2023 Transmission Plan as part of its analysis of the Trout Canyon Lugo 500 kV Line. This evaluation will assist with explaining the impact of the previously approved projects and the additional benefits that the Trout-Canyon – Lugo 500 kV line could provide. This information will also assist with assessing if the Trout-Canyon – Lugo 500 kV project is still necessary.
Second, CAISO should compare the costs and benefits of the Trout Canyon – Lugo 500 kV project with the proposed Mead – Adelanto Project Upgrade (MAP Upgrade project). The MAP Upgrade project would convert the existing Mead – Adelanto line from High-Voltage Alternating Current operation (HVAC) to High-Voltage Direct Current (HVDC) operation. This conversion is anticipated to increase the Mead - Adelanto line capacity from 1,291 megawatt (MW) to 3,500 MW.[2] As a result, the MAP Upgrade project would provide increased transmission capacity between southern California and southern Nevada, and specifically along the Eldorado-Lugo corridor. This project alternative is also anticipated to cost $1.1 billion, which is significantly less than the proposed $2 billion for the Trout Canyon-Lugo 500 kV project.[3] It is worth noting that the Trout Canyon-Lugo 500 kV line would need to establish a new transmission corridor across the California desert and for this reason is a riskier project than the proposed MAP Upgrade project, which involves upgrading an existing line.
[1] Base Portfolio Preliminary PCM Results, CAISO, November 16, 2023 at p.172.
[2] Letter regarding Alternative to the CAISO proposed Trout Canyon – Lugo 500 kV transmission line, Lotus Infrastructure Partners, April 25, 2023 at p. 1.
[3] 2015-2016 California ISO Transmission Plan, CAISO, March 28, 2016 at p. 111.
8.
Please provide any additional comments on the November 16, 2023 Transmission Planning Process Stakeholder Meeting.
Reliability Project Update
Cal Advocates appreciates that CAISO is not moving forward with the conceptual reliability projects that PG&E presented at the September 27, 2023 Reliability meeting. Providing PG&E with additional time to evaluate mitigation options to address identified reliability issues including considering GETs should result in cost savings for ratepayers.
California Independent System Operator (CAISO) should coordinate with the California Public Utilities Commission (CPUC) to incorporate non-CPUC load-serving entities’ (LSEs) planned resources into the busbar mapping process, rather than amend the busbar mapping results on a post-hoc basis.
In its Interconnection Process Enhancements (IPE) Initiative Phase 2 Straw Proposal, CAISO states, “In addition to the portfolios received by the CPUC for the annual transmission planning process, the ISO will coordinate with the Local Regulatory Authorities (LRAs) and non-CPUC jurisdictional entities to determine their approved resources in their individual IRPs to include in the transmission planning analysis.” [1] However, non-CPUC-jurisdictional LSEs’ planned resources should be taken into consideration during the joint CAISO-CPUC-California Energy Commission (CEC) busbar mapping process, to the extent possible. The inclusion of non-CPUC jurisdictional LSEs’ future resources on a post-hoc basis in the transmission planning analysis may result in suboptimal ratepayer outcomes in the event that the busbar mapping process would have produced a different set of mapped resources and transmission upgrades had the full suite of non-CPUC-jurisdictional entities’ planned resources been taken into consideration in the CPUC’s Integrated Resource Planning (IRP). The IRP process already includes some non-CPUC-jurisdictional entities’ planned resources in the list of baseline resources. However, these resources may not reflect all planned resources, due to the information asymmetry inherent in the CPUC’s lack of jurisdiction over the IRP activities of other LRAs’ and LSEs.[2] For example, the CPUC’s IRP modeling may not reflect all generic resources that non-CPUC-jurisdictional entities may be planning in future study years to meet their Renewables Portfolio Standard and greenhouse gas emissions reduction needs. As the CPUC lacks jurisdiction to require other LRAs to provide any such information, the CPUC may be unable to improve the IRP modeling inputs and assumptions unilaterally to model any missing non-CPUC-jurisdictional entities’ planned resources.
However, the CAISO and CEC have jurisdiction to require such information from the non-CPUC-jurisdictional entities by way of their CAISO roles as LRAs[3] and their IRP obligations before the CEC.[4] In addition, the CAISO and CEC actively collaborate with the CPUC in the IRP’s busbar mapping process. Therefore, the CAISO should not be content to amend the busbar mapping results on an ad-hoc basis to reflect the transmission deliverability needs of the non-CPUC-jurisdictional entities.
Instead, the CAISO should proactively collaborate with the CPUC and CEC. Ideally, the CPUC would have information on any non-CPUC-jurisdictional entities’ planned resources well before the busbar mapping process begins – early enough in the IRP process for the IRP modeling to address the effects of non-CPUC-jurisdictional entities’ planned resources and associated transmission deliverability needs. However, the non-CPUC-jurisdictional LSEs have varying schedules and levels of detail for their own planning activities. The timing and detail of the non-CPUC-jurisdictional entities’ plans may or may not allow for early incorporation into the CPUC’s IRP modeling assumptions. If early incorporation proves infeasible, then the CAISO should work with the CPUC and CEC to incorporate non-CPUC-jurisdictional entities’ planned resources directly into the busbar mapping process.
[1] CAISO, 2023 Interconnection Process Enhancements Track 2 Straw Proposal, September 21, 2023, at 19.
[2] The CEC has jurisdiction for review of publicly owned utilities’ (POUs) IRP filings pursuant to Public Utilities Code Section 9622. The CPUC lacks jurisdiction to require POUs to submit IRP-related information directly to the CPUC. In addition, not all POUs file IRPs, and those that do may have outdated IRPs. Pursuant to Public Utilities Code Section 9621, POU IRP requirements apply only to POUs with 700 gigawatt-hours of annual demand, and POU IRPs need be updated only once every five years.
[3] Section 40 of the CAISO Tariff places various resource planning responsibilities upon each LRA, such as the setting of Planning Reserve Margins and the accreditation of Qualifying Capacity values for specific resource(s) or resource type(s). The CAISO’s 2023 Interconnection Process Enhancements Track 2 Straw Proposal more generally proposes to work collaboratively with LRAs to incorporate non-CPUC-jurisdictional LSEs’ preferred planned resources in the CAISO’s transmission planning process.
[4] Public Utilities Code Section 9622.
California Western Grid Development, LLC
Submitted 12/04/2023, 04:56 pm
1.
Please provide your organization’s comments on the Recommended Reliability Projects less than $50 million for the North Region.
Cal Western Grid has no comment
2.
Please provide your organization’s comments on the Recommended Reliability Projects less than $50 million for the South Region.
Cal Western Grid has no comment
3.
Please provide your organization’s comments on the MIC Expansion Requests.
Cal Western Grid has no comment
4.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the SCE & GLW areas.
Comments of California Western Grid LLC
on CAISO’s November 16, 2023, Stakeholder Presentation
For the 2023-2024 Transmission Planning Process
Three Rivers Energy Development, LLC (TRED) is an Independent Transmission Developer that is developing the Pacific Transmission Expansion Project (“PTE Project” or “PTEP”) on behalf of California Western Grid Development, LLC. (“California Western Grid” or “CWG”). The PTE Project is a 2,000 MW controllable HVDC subsea transmission cable that the California Independent System Operator (“CAISO”) has found will allow new and renewable energy supply including new offshore wind, available to the Diablo Canyon 500 kV switchyard, or Morro Bay to be delivered to the LA Basin to reduce local capacity requirements while also solving other significant reliability, economic and public policy needs.
Cal Western Grid found the CAISO September 26 and November 16 2023-24 TPP Stakeholder Meetings to be extremely valuable and informative. We appreciate all the expertise and hard work CAISO staff have applied to bring us to this point in the TPP.
Cal Western Grid will be making three primary requests of CAISO in our comments today.
- Evaluate the cumulative reliability, economic and policy benefits of PTEP - and present CAISOs findings in a single tabulation in the 2023-24 TPP draft transmission plan on March 31, 2024.
- Update the TEAM methodology analysis of PTEP - When evaluating Local RA Benefits of PTEP using the TEAM methodology, recognize that by 2035 the marginal system RA resource will be utility scale batteries and not gas fired generation.
- Act on the urgency to move forward with least regrets long lead time transmission solutions for transmission constrained local areas and recommend approval of an undersea transmission solution from Central California to the LA Basin to the CAISO Board in this 2023-24 TPP.
Evaluate the Cumulative Reliability, Economic and Policy benefits of the PTEP project.
Cal Western Grid appreciates CAISO’s intent to evaluate both reliability and economic benefits. PTEP as part of the 2023-24 TPP (11/16 Stakeholder Presentation slides 11 and 183). In addition to reliability and economic benefits, Cal Western Grid also believes PTEP provides significant public policy benefits.
We request the CAISO evaluate the benefits of the PTEP wholistically, summing the cumulative reliability, economic and policy benefits of the proposed project, and tabulate and present the summary cumulative findings in a single place in the 3/31/24 CAISO draft Transmission Plan.
Our concern is that while each individual project benefit (reliability, economic and policy) may not in of itself justify approval of PTEP transmission solution, when the individual benefits are added together, they will more than justify moving forward with a subsea transmission solution that brings power from Central California directly into the transmission constrained Western LA Basin.[1] By presenting a finding on the cumulative benefits of a subsea transmission solution, stakeholders will be reassured that the project was evaluated across all of the benefits and value streams the project has to offer.
Cal Western Grid has specific requests to help shape CAISO evaluation of each of the PTEP reliability, economic and policy benefits.[2]
Reliability Benefits of PTEP - While reliability needs are often studied as small, targeted solutions, PTEP offers a broad spectrum of reliability benefits for Path 26 and the LA Basin. As we stated in our 10/13/23 study request, we urge the CAISO to apply a broad strategic approach to evaluating the reliability benefits offered by PTEP. To look beyond a single reliability benefit and instead evaluate PTEPs cumulative ability to (1) reduce congestion on Path 26; (2) eliminate numerous P6 and P7 contingencies on the SCE Main and Western LA Basin systems; and (3) eliminate uncertainty in meeting the battery recharging requirements in the LA Basin.
All three of which were noted as reliability needs in the CAISO September 26 Stakeholder Meeting and all of which can be alleviated by PTEP.
Economic Benefits of PTEP – Cal Western is pleased the CAISO accepted Cal Western Grid’s Economic planning study request for PTEP (slide 183/187 of CAISO November 16 presentation, and Page 77 of the CAISO 2023-24 TPP Final Study Plan dated 8/15/23).
PTEP offers a multitude of economic benefits, some of which can be quantified using the TEAM methodology and many of which are not included in TEAMs restricted view of project economic benefits.
The most notable benefits that can be quantified applying the TEAM methodology include:
- Production Benefits
- System Adequacy Benefits
- Local Resource Adequacy Benefits
- Congestion relief benefits
Cal Western commissioned a study by E3 Consulting in 2022 to take a fresh look at the economics of the PTEP Project. Using the TEAM methodology E3 found that even if gas plants are not retired in the LA Basin by 2035 the PTEP yields a b/c ratio of 0.58 to 0.64. The key difference between the E3 analysis and traditional CAISO TEAM evaluation is the way Local Capacity benefits are quantified. E3 concluded utility scale batteries are the system marginal resource by 2035, not gas fired generation. However, E3 assumed that gas generation continued to be the marginal resource for local RA in 2035. We urge CAISO to revise its past practice of assuming gas generation is the marginal system resource for both system RA and Local RA in 2035.
Cal Western believes there are also glaring omissions from TEAM methodology Benefits Calculations, for example none of the following have been historically quantified:
- GHG and Renewable Energy Credit (REC) Benefits
- Local Air Emissions benefits (NOx, PM2.5, SOx)
- Reduced Risk of Wildfires
- Reduced need for Aliso Canyon Storage Facility
The E3 study of PTEP economics from 2022 did quantify the avoided REC and GHG benefits but attempting to quantify additional benefits was beyond the scope of the study. Simply adding a reasonable value for PTEPs avoided REC and GHG costs raised the b/c ratio to 0.62-0.68. Again, this b/c ratio did not assume any gas plant retirements in the LA Basin.
Cal Western Grid encourages the CAISO to at a minimum quantify REC and GHG benefits as part of its TEAM evaluation of PTEP in the 2023-24 TPP. CAISO can review the methodology E3 used to evaluate REC and GHG benefits by looking at Cal Western Grid 2022-23 TPP Technical Appendix A (page 32-33) of our Request Window Submission Form submitted on 10/14/22.
Finally, E3 prepared a only a partial update of the economic analysis of PTEP in September 2023 but concluded that given the 2023-24 TPP increased loads and significant new resource additions in the preferred portfolio, the TEAM economic benefits of PTEP would likely be higher than they found in their initial 2022 economic benefits study.
Public Policy Benefits of PTEP - The CAISO evaluation of public policy benefits in the 2022-23 TPP was focused on “Deliverability” and “System Resource Adequacy”. The public policy transmission solutions that were approved in the 2022-23 TPP had the benefit of removing constraints that could hamper bringing clean power from generators to the high voltage 230/500 kV backbone system. However, transmission needed to deliver that power to location constrained load pockets such as the LA Basin was not the focus.
Cal Western Grid applauds the CAISO 2022-23 TPP approval of Public Policy transmission solutions to bring power from renewable energy sources to the high voltage 230/500 kV backbone system, which the CAISO called ‘deliverability’ solutions. However, failing to evaluate and approve transmission solutions that allow renewable power to move from the high voltage 230/500 kV backbone system into transmission constrained load centers is a critical omission that SB 887 requires be addressed.
Cal Western Grid believes that the CPUC is still required to provide gas plant guidance to the CAISO under SB 887, however, CAISO has already received sufficient guidance from the CPUC to proceed with much needed transmission into transmission constrained local areas. The preferred resource portfolio the CPUC has already transmitted to CAISO for the 2023-24 TPP combined with the public policy guidance articulated in SB 887 is sufficient for the CAISO to approve a few initial projects that perform well under multiple scenarios and support reduced reliance on gas plants in transmission constrained load pockets. The only thing CAISO must do is to expand the definition of ‘deliverability’ the way SB 887 requires; Section 1 (h) (3) asks the CAISO to plan and approve transmission that “eliminate(s) transmission constraints that prevent electrical generation resources from delivery to the wider grid and that prevent importing energy into load pockets.”
In the 2022-23 TPP the CAISO approved numerous deliverability solutions that allowed electrical resources to be delivered to the grid. The CAISO did this based on the portfolio provided by the CPUC. What the CAISO failed to do was approve transmission solutions to eliminate transmission constraints that prevent importing energy into load pockets.
It appears to Cal Western Grid that the CAISO is about to repeat this material omission for public policy transmission approvals in the 2023-24 TPP. From the staff overview of Slides 33 and 34 at the 11-16-23 Stakeholder Meeting it appears to Cal Western Grid that CAISO Staff intends to define deliverability narrowly once again, as the ability to deliver power from resources to the high voltage grid, and not address eliminating transmission constraints that prevent importing energy into load pockets. In the 2023-24 TP the CAISO must broaden its definition of deliverability to include transmission needed to bring energy into transmission constrained load pockets.
Turning to the language of SB 887, it is clear the legislature asks CAISO recognize the policies set forth in SB 887:
‘…it is the intent of the Legislature that the Independent System Operator shall take notice of the state policies expressed in this section” SB 887 Section 1 (c).
And Section 1 (h)(3) of SB 887 makes it clear that state policy is to eliminate transmission constraints that prevent importing energy into load pockets (transmission constrained load pockets):
“It is the policy of the state that planning for new transmission facilities considers the following goals: …. (3) eliminate constraints that prevent electrical generation resources from delivering to the wider grid and that prevent importing energy into load pockets.”
And in Section 1 (e) (4) (A) SB 887 provides policy guidance regarding when transmission should be in place to eliminate constraints into local capacity areas, i.e., not later than 2035:
“Providing resource projections that, combined with transmission capacity expansions, are expected to substantially reduce, no later than 2035, the need to rely on nonpreferred resources in local capacity areas.”
The State policy is clear, and the CPUC and CEC have already given load forecasts with a resource portfolio to the CAISO that enables the CAISO to approve the transmission SB 887 Section 1 (h) (3) sets forth as public policy, (i.e., transmission that removes constraints that prevent importing energy into load pockets).
All that is needed is for the CAISO to expand its definition of ‘deliverability’ to embrace the scope required under SB 887. Deliverability that includes both bringing power from resource zones to the high voltage grid and to transmission constrained load pockets.
Cal Western Grid understands that the CAISO has repeatedly asked for gas plant guidance from the CPUC and a plan for reducing reliance on gas generation. Cal Western Grid believes that guidance, including a retirement plan for gas fired generation would facilitate CAISO planning for transmission solutions, but while this required guidance has not been provided, it should not be necessary in order to get started now, in the current 2023-24 TPP, for approving transmission to load centers as envisioned in SB 887.
In fact, waiting for a CPUC gas plant retirement plan is a luxury the CAISO can no longer afford. The 2023-24 TPP resource portfolios provided by the CPUC, once again, do not contain a plan for reducing reliance on gas plants during the planning horizon. Even more concerning is the CPUC on October 5, 2023, issued its proposed preferred planning portfolio for the 2024-25 TPP without any provision for gas plant reductions or guidance for the CAISO.
Again, the CPUC proposed a Preferred Resource Portfolio that does not plan for meaningfully reduced reliance on gas plants in transmission constrained local areas, or even a plan for reducing reliance on system wide gas plants during the entire planning horizon, through 2039.
We urge CAISO recognize the CPUC preferred portfolio that the CPUC has already provided is enough to start approving least regrets transmission solutions that will provide substantial reliability and economic benefits and will be needed to meet California’s SB 887 policy objectives.
As the CAISO knows well, long lead time transmission approved by the CAISO in the 2023-24 TPP is subject to competitive bidding to select a sponsor. We recognize CAISO Management intends to seek Board Approval of major transmission projects at the Board Meeting in May 2024. If a project were approved by CAISO Board in May 2024 as part of the 2023-24 TPP, a sponsor would not, under CAISO’s phase 3 competitive process, be selected until the very end of 2024 or more likely early 2025. Only then can the more than decade-long timeframe for permitting and construction begin. SB 887 requires the Commission to plan to reduce reliance on gas plants in location constrained load centers by 2035. Projects approved by CAISO which do not have a sponsor until early 2025 cannot realistically be expected to be operational by 2035, and the more likely operational date would be in the 2036-2038 timeframe, which fails the policy requirements of the state. This is because the challenge for siting and permitting requirements for significant new transmission projects is long and arduous. This coupled with recent supply chain issues exacerbated by the worldwide growing demand for new transmission cable and equipment that is being driven by the need to reduce reliance on fossil generation.
While Cal Western Grid continues to encourage CAISO to proactively reach out to the CPUC and CEC, Cal Western believes the CAISO can and should make a determination of need for PTEP in this 2023-24 TPP without waiting for further guidance or a gas plant retirement plan from the CPUC.
If CAISO reviews the cumulative benefits of PTEP, even without gas plants being retired, the TEAM methodology alone can drive a b/c ratio that approaches or exceeds 1.0. When the additional reliability benefits, economic benefits that are not quantified in TEAM and urgency to get started with needed policy driven transmission, as required by SB 887 are considered cumulatively, CAISO should conclude approval for PTEP is warranted in the 2023-24 TPP.
Cal Western believes the CAISO approval would receive very little pushback. Multiple stakeholders have filed comments at the CPUC expressing the need to get going with needed new transmission. And importantly, even the CPUC said when transmitting the resource portfolios for the 2023-24 TPP to CAISO:
“If California is to meet its aggressive reliability and environmental goals, more transmission will be needed to be planned and built ahead of generation and storage development, and it is just a matter of exactly when, and not if, the transmission will be needed.”[3]
It is far past time for CAISO to start approving least regrets transmission solutions that will provide substantial reliability and economic benefits that will be needed to meet California’s SB887 policy objectives.
PTEP is a least regrets option that, if triggered in the 2023-24 TPP, can provide a solution to the transmission constrained West LA load pocket and provide substantial economic and reliability benefits.
California Western Grid appreciates the opportunity to offer its views on these critical issues and stands ready to answer any questions or to provide any additional information CAISO may need.
Respectfully submitted,
Marty Walicki, Managing Partner December 4, 2023.
[1] Cal Western has interchangeably used a specific project name (PTEP) and a generic transmission solution described as a subsea transmission project from Central California to Western LA Basin. Cal Western understands the CAISO approves transmission solutions, not specific projects. Cal Western also understands that if a project like PTEP were approved by CAISO the project sponsor would only be selected competitively in the 2023-24 TPP phase three.
[2] Each of these benefits are discussed in more detail in our October 13, 2023, filing.
[3] CPUC Decision 23-02-040, Ordering Supplemental Mid-Term Reliability Procurement (2026-2027) and Transmitting Electric Resource Portfolios to California Independent System Operator for Transmission Planning Portfolios, pp. 48- 49.
5.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the SDG&E area
Cal Western Grid has no comment
6.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the PG&E area.
Cal Western Grid has no comment
7.
Please provide your organization’s comments on the Preliminary Economic Analysis Results.
Comments of California Western Grid LLC
on CAISO’s November 16, 2023, Stakeholder Presentation
For the 2023-2024 Transmission Planning Process
Three Rivers Energy Development, LLC (TRED) is an Independent Transmission Developer that is developing the Pacific Transmission Expansion Project (“PTE Project” or “PTEP”) on behalf of California Western Grid Development, LLC. (“California Western Grid” or “CWG”). The PTE Project is a 2,000 MW controllable HVDC subsea transmission cable that the California Independent System Operator (“CAISO”) has found will allow new and renewable energy supply including new offshore wind, available to the Diablo Canyon 500 kV switchyard, or Morro Bay to be delivered to the LA Basin to reduce local capacity requirements while also solving other significant reliability, economic and public policy needs.
Cal Western Grid found the CAISO September 26 and November 16 2023-24 TPP Stakeholder Meetings to be extremely valuable and informative. We appreciate all the expertise and hard work CAISO staff have applied to bring us to this point in the TPP.
Cal Western Grid will be making three primary requests of CAISO in our comments today.
- Evaluate the cumulative reliability, economic and policy benefits of PTEP - and present CAISOs findings in a single tabulation in the 2023-24 TPP draft transmission plan on March 31, 2024.
- Update the TEAM methodology analysis of PTEP - When evaluating Local RA Benefits of PTEP using the TEAM methodology, recognize that by 2035 the marginal system RA resource will be utility scale batteries and not gas fired generation.
- Act on the urgency to move forward with least regrets long lead time transmission solutions for transmission constrained local areas and recommend approval of an undersea transmission solution from Central California to the LA Basin to the CAISO Board in this 2023-24 TPP.
Evaluate the Cumulative Reliability, Economic and Policy benefits of the PTEP project.
Cal Western Grid appreciates CAISO’s intent to evaluate both reliability and economic benefits. PTEP as part of the 2023-24 TPP (11/16 Stakeholder Presentation slides 11 and 183). In addition to reliability and economic benefits, Cal Western Grid also believes PTEP provides significant public policy benefits.
We request the CAISO evaluate the benefits of the PTEP wholistically, summing the cumulative reliability, economic and policy benefits of the proposed project, and tabulate and present the summary cumulative findings in a single place in the 3/31/24 CAISO draft Transmission Plan.
Our concern is that while each individual project benefit (reliability, economic and policy) may not in of itself justify approval of PTEP transmission solution, when the individual benefits are added together, they will more than justify moving forward with a subsea transmission solution that brings power from Central California directly into the transmission constrained Western LA Basin.[1] By presenting a finding on the cumulative benefits of a subsea transmission solution, stakeholders will be reassured that the project was evaluated across all of the benefits and value streams the project has to offer.
Cal Western Grid has specific requests to help shape CAISO evaluation of each of the PTEP reliability, economic and policy benefits.[2]
Reliability Benefits of PTEP - While reliability needs are often studied as small, targeted solutions, PTEP offers a broad spectrum of reliability benefits for Path 26 and the LA Basin. As we stated in our 10/13/23 study request, we urge the CAISO to apply a broad strategic approach to evaluating the reliability benefits offered by PTEP. To look beyond a single reliability benefit and instead evaluate PTEPs cumulative ability to (1) reduce congestion on Path 26; (2) eliminate numerous P6 and P7 contingencies on the SCE Main and Western LA Basin systems; and (3) eliminate uncertainty in meeting the battery recharging requirements in the LA Basin.
All three of which were noted as reliability needs in the CAISO September 26 Stakeholder Meeting and all of which can be alleviated by PTEP.
Economic Benefits of PTEP – Cal Western is pleased the CAISO accepted Cal Western Grid’s Economic planning study request for PTEP (slide 183/187 of CAISO November 16 presentation, and Page 77 of the CAISO 2023-24 TPP Final Study Plan dated 8/15/23).
PTEP offers a multitude of economic benefits, some of which can be quantified using the TEAM methodology and many of which are not included in TEAMs restricted view of project economic benefits.
The most notable benefits that can be quantified applying the TEAM methodology include:
- Production Benefits
- System Adequacy Benefits
- Local Resource Adequacy Benefits
- Congestion relief benefits
Cal Western commissioned a study by E3 Consulting in 2022 to take a fresh look at the economics of the PTEP Project. Using the TEAM methodology E3 found that even if gas plants are not retired in the LA Basin by 2035 the PTEP yields a b/c ratio of 0.58 to 0.64. The key difference between the E3 analysis and traditional CAISO TEAM evaluation is the way Local Capacity benefits are quantified. E3 concluded utility scale batteries are the system marginal resource by 2035, not gas fired generation. However, E3 assumed that gas generation continued to be the marginal resource for local RA in 2035. We urge CAISO to revise its past practice of assuming gas generation is the marginal system resource for both system RA and Local RA in 2035.
Cal Western believes there are also glaring omissions from TEAM methodology Benefits Calculations, for example none of the following have been historically quantified:
- GHG and Renewable Energy Credit (REC) Benefits
- Local Air Emissions benefits (NOx, PM2.5, SOx)
- Reduced Risk of Wildfires
- Reduced need for Aliso Canyon Storage Facility
The E3 study of PTEP economics from 2022 did quantify the avoided REC and GHG benefits but attempting to quantify additional benefits was beyond the scope of the study. Simply adding a reasonable value for PTEPs avoided REC and GHG costs raised the b/c ratio to 0.62-0.68. Again, this b/c ratio did not assume any gas plant retirements in the LA Basin.
Cal Western Grid encourages the CAISO to at a minimum quantify REC and GHG benefits as part of its TEAM evaluation of PTEP in the 2023-24 TPP. CAISO can review the methodology E3 used to evaluate REC and GHG benefits by looking at Cal Western Grid 2022-23 TPP Technical Appendix A (page 32-33) of our Request Window Submission Form submitted on 10/14/22.
Finally, E3 prepared a only a partial update of the economic analysis of PTEP in September 2023 but concluded that given the 2023-24 TPP increased loads and significant new resource additions in the preferred portfolio, the TEAM economic benefits of PTEP would likely be higher than they found in their initial 2022 economic benefits study.
Public Policy Benefits of PTEP - The CAISO evaluation of public policy benefits in the 2022-23 TPP was focused on “Deliverability” and “System Resource Adequacy”. The public policy transmission solutions that were approved in the 2022-23 TPP had the benefit of removing constraints that could hamper bringing clean power from generators to the high voltage 230/500 kV backbone system. However, transmission needed to deliver that power to location constrained load pockets such as the LA Basin was not the focus.
Cal Western Grid applauds the CAISO 2022-23 TPP approval of Public Policy transmission solutions to bring power from renewable energy sources to the high voltage 230/500 kV backbone system, which the CAISO called ‘deliverability’ solutions. However, failing to evaluate and approve transmission solutions that allow renewable power to move from the high voltage 230/500 kV backbone system into transmission constrained load centers is a critical omission that SB 887 requires be addressed.
Cal Western Grid believes that the CPUC is still required to provide gas plant guidance to the CAISO under SB 887, however, CAISO has already received sufficient guidance from the CPUC to proceed with much needed transmission into transmission constrained local areas. The preferred resource portfolio the CPUC has already transmitted to CAISO for the 2023-24 TPP combined with the public policy guidance articulated in SB 887 is sufficient for the CAISO to approve a few initial projects that perform well under multiple scenarios and support reduced reliance on gas plants in transmission constrained load pockets. The only thing CAISO must do is to expand the definition of ‘deliverability’ the way SB 887 requires; Section 1 (h) (3) asks the CAISO to plan and approve transmission that “eliminate(s) transmission constraints that prevent electrical generation resources from delivery to the wider grid and that prevent importing energy into load pockets.”
In the 2022-23 TPP the CAISO approved numerous deliverability solutions that allowed electrical resources to be delivered to the grid. The CAISO did this based on the portfolio provided by the CPUC. What the CAISO failed to do was approve transmission solutions to eliminate transmission constraints that prevent importing energy into load pockets.
It appears to Cal Western Grid that the CAISO is about to repeat this material omission for public policy transmission approvals in the 2023-24 TPP. From the staff overview of Slides 33 and 34 at the 11-16-23 Stakeholder Meeting it appears to Cal Western Grid that CAISO Staff intends to define deliverability narrowly once again, as the ability to deliver power from resources to the high voltage grid, and not address eliminating transmission constraints that prevent importing energy into load pockets. In the 2023-24 TP the CAISO must broaden its definition of deliverability to include transmission needed to bring energy into transmission constrained load pockets.
Turning to the language of SB 887, it is clear the legislature asks CAISO recognize the policies set forth in SB 887:
‘…it is the intent of the Legislature that the Independent System Operator shall take notice of the state policies expressed in this section” SB 887 Section 1 (c).
And Section 1 (h)(3) of SB 887 makes it clear that state policy is to eliminate transmission constraints that prevent importing energy into load pockets (transmission constrained load pockets):
“It is the policy of the state that planning for new transmission facilities considers the following goals: …. (3) eliminate constraints that prevent electrical generation resources from delivering to the wider grid and that prevent importing energy into load pockets.”
And in Section 1 (e) (4) (A) SB 887 provides policy guidance regarding when transmission should be in place to eliminate constraints into local capacity areas, i.e., not later than 2035:
“Providing resource projections that, combined with transmission capacity expansions, are expected to substantially reduce, no later than 2035, the need to rely on nonpreferred resources in local capacity areas.”
The State policy is clear, and the CPUC and CEC have already given load forecasts with a resource portfolio to the CAISO that enables the CAISO to approve the transmission SB 887 Section 1 (h) (3) sets forth as public policy, (i.e., transmission that removes constraints that prevent importing energy into load pockets).
All that is needed is for the CAISO to expand its definition of ‘deliverability’ to embrace the scope required under SB 887. Deliverability that includes both bringing power from resource zones to the high voltage grid and to transmission constrained load pockets.
Cal Western Grid understands that the CAISO has repeatedly asked for gas plant guidance from the CPUC and a plan for reducing reliance on gas generation. Cal Western Grid believes that guidance, including a retirement plan for gas fired generation would facilitate CAISO planning for transmission solutions, but while this required guidance has not been provided, it should not be necessary in order to get started now, in the current 2023-24 TPP, for approving transmission to load centers as envisioned in SB 887.
In fact, waiting for a CPUC gas plant retirement plan is a luxury the CAISO can no longer afford. The 2023-24 TPP resource portfolios provided by the CPUC, once again, do not contain a plan for reducing reliance on gas plants during the planning horizon. Even more concerning is the CPUC on October 5, 2023, issued its proposed preferred planning portfolio for the 2024-25 TPP without any provision for gas plant reductions or guidance for the CAISO.
Again, the CPUC proposed a Preferred Resource Portfolio that does not plan for meaningfully reduced reliance on gas plants in transmission constrained local areas, or even a plan for reducing reliance on system wide gas plants during the entire planning horizon, through 2039.
We urge CAISO recognize the CPUC preferred portfolio that the CPUC has already provided is enough to start approving least regrets transmission solutions that will provide substantial reliability and economic benefits and will be needed to meet California’s SB 887 policy objectives.
As the CAISO knows well, long lead time transmission approved by the CAISO in the 2023-24 TPP is subject to competitive bidding to select a sponsor. We recognize CAISO Management intends to seek Board Approval of major transmission projects at the Board Meeting in May 2024. If a project were approved by CAISO Board in May 2024 as part of the 2023-24 TPP, a sponsor would not, under CAISO’s phase 3 competitive process, be selected until the very end of 2024 or more likely early 2025. Only then can the more than decade-long timeframe for permitting and construction begin. SB 887 requires the Commission to plan to reduce reliance on gas plants in location constrained load centers by 2035. Projects approved by CAISO which do not have a sponsor until early 2025 cannot realistically be expected to be operational by 2035, and the more likely operational date would be in the 2036-2038 timeframe, which fails the policy requirements of the state. This is because the challenge for siting and permitting requirements for significant new transmission projects is long and arduous. This coupled with recent supply chain issues exacerbated by the worldwide growing demand for new transmission cable and equipment that is being driven by the need to reduce reliance on fossil generation.
While Cal Western Grid continues to encourage CAISO to proactively reach out to the CPUC and CEC, Cal Western believes the CAISO can and should make a determination of need for PTEP in this 2023-24 TPP without waiting for further guidance or a gas plant retirement plan from the CPUC.
If CAISO reviews the cumulative benefits of PTEP, even without gas plants being retired, the TEAM methodology alone can drive a b/c ratio that approaches or exceeds 1.0. When the additional reliability benefits, economic benefits that are not quantified in TEAM and urgency to get started with needed policy driven transmission, as required by SB 887 are considered cumulatively, CAISO should conclude approval for PTEP is warranted in the 2023-24 TPP.
Cal Western believes the CAISO approval would receive very little pushback. Multiple stakeholders have filed comments at the CPUC expressing the need to get going with needed new transmission. And importantly, even the CPUC said when transmitting the resource portfolios for the 2023-24 TPP to CAISO:
“If California is to meet its aggressive reliability and environmental goals, more transmission will be needed to be planned and built ahead of generation and storage development, and it is just a matter of exactly when, and not if, the transmission will be needed.”[3]
It is far past time for CAISO to start approving least regrets transmission solutions that will provide substantial reliability and economic benefits that will be needed to meet California’s SB887 policy objectives.
PTEP is a least regrets option that, if triggered in the 2023-24 TPP, can provide a solution to the transmission constrained West LA load pocket and provide substantial economic and reliability benefits.
California Western Grid appreciates the opportunity to offer its views on these critical issues and stands ready to answer any questions or to provide any additional information CAISO may need.
Respectfully submitted,
Marty Walicki, Managing Partner December 4, 2023.
[1] Cal Western has interchangeably used a specific project name (PTEP) and a generic transmission solution described as a subsea transmission project from Central California to Western LA Basin. Cal Western understands the CAISO approves transmission solutions, not specific projects. Cal Western also understands that if a project like PTEP were approved by CAISO the project sponsor would only be selected competitively in the 2023-24 TPP phase three.
[2] Each of these benefits are discussed in more detail in our October 13, 2023, filing.
[3] CPUC Decision 23-02-040, Ordering Supplemental Mid-Term Reliability Procurement (2026-2027) and Transmitting Electric Resource Portfolios to California Independent System Operator for Transmission Planning Portfolios, pp. 48- 49.
8.
Please provide any additional comments on the November 16, 2023 Transmission Planning Process Stakeholder Meeting.
Comments of California Western Grid LLC
on CAISO’s November 16, 2023, Stakeholder Presentation
For the 2023-2024 Transmission Planning Process
Three Rivers Energy Development, LLC (TRED) is an Independent Transmission Developer that is developing the Pacific Transmission Expansion Project (“PTE Project” or “PTEP”) on behalf of California Western Grid Development, LLC. (“California Western Grid” or “CWG”). The PTE Project is a 2,000 MW controllable HVDC subsea transmission cable that the California Independent System Operator (“CAISO”) has found will allow new and renewable energy supply including new offshore wind, available to the Diablo Canyon 500 kV switchyard, or Morro Bay to be delivered to the LA Basin to reduce local capacity requirements while also solving other significant reliability, economic and public policy needs.
Cal Western Grid found the CAISO September 26 and November 16 2023-24 TPP Stakeholder Meetings to be extremely valuable and informative. We appreciate all the expertise and hard work CAISO staff have applied to bring us to this point in the TPP.
Cal Western Grid will be making three primary requests of CAISO in our comments today.
- Evaluate the cumulative reliability, economic and policy benefits of PTEP - and present CAISOs findings in a single tabulation in the 2023-24 TPP draft transmission plan on March 31, 2024.
- Update the TEAM methodology analysis of PTEP - When evaluating Local RA Benefits of PTEP using the TEAM methodology, recognize that by 2035 the marginal system RA resource will be utility scale batteries and not gas fired generation.
- Act on the urgency to move forward with least regrets long lead time transmission solutions for transmission constrained local areas and recommend approval of an undersea transmission solution from Central California to the LA Basin to the CAISO Board in this 2023-24 TPP.
Evaluate the Cumulative Reliability, Economic and Policy benefits of the PTEP project.
Cal Western Grid appreciates CAISO’s intent to evaluate both reliability and economic benefits. PTEP as part of the 2023-24 TPP (11/16 Stakeholder Presentation slides 11 and 183). In addition to reliability and economic benefits, Cal Western Grid also believes PTEP provides significant public policy benefits.
We request the CAISO evaluate the benefits of the PTEP wholistically, summing the cumulative reliability, economic and policy benefits of the proposed project, and tabulate and present the summary cumulative findings in a single place in the 3/31/24 CAISO draft Transmission Plan.
Our concern is that while each individual project benefit (reliability, economic and policy) may not in of itself justify approval of PTEP transmission solution, when the individual benefits are added together, they will more than justify moving forward with a subsea transmission solution that brings power from Central California directly into the transmission constrained Western LA Basin.[1] By presenting a finding on the cumulative benefits of a subsea transmission solution, stakeholders will be reassured that the project was evaluated across all of the benefits and value streams the project has to offer.
Cal Western Grid has specific requests to help shape CAISO evaluation of each of the PTEP reliability, economic and policy benefits.[2]
Reliability Benefits of PTEP - While reliability needs are often studied as small, targeted solutions, PTEP offers a broad spectrum of reliability benefits for Path 26 and the LA Basin. As we stated in our 10/13/23 study request, we urge the CAISO to apply a broad strategic approach to evaluating the reliability benefits offered by PTEP. To look beyond a single reliability benefit and instead evaluate PTEPs cumulative ability to (1) reduce congestion on Path 26; (2) eliminate numerous P6 and P7 contingencies on the SCE Main and Western LA Basin systems; and (3) eliminate uncertainty in meeting the battery recharging requirements in the LA Basin.
All three of which were noted as reliability needs in the CAISO September 26 Stakeholder Meeting and all of which can be alleviated by PTEP.
Economic Benefits of PTEP – Cal Western is pleased the CAISO accepted Cal Western Grid’s Economic planning study request for PTEP (slide 183/187 of CAISO November 16 presentation, and Page 77 of the CAISO 2023-24 TPP Final Study Plan dated 8/15/23).
PTEP offers a multitude of economic benefits, some of which can be quantified using the TEAM methodology and many of which are not included in TEAMs restricted view of project economic benefits.
The most notable benefits that can be quantified applying the TEAM methodology include:
- Production Benefits
- System Adequacy Benefits
- Local Resource Adequacy Benefits
- Congestion relief benefits
Cal Western commissioned a study by E3 Consulting in 2022 to take a fresh look at the economics of the PTEP Project. Using the TEAM methodology E3 found that even if gas plants are not retired in the LA Basin by 2035 the PTEP yields a b/c ratio of 0.58 to 0.64. The key difference between the E3 analysis and traditional CAISO TEAM evaluation is the way Local Capacity benefits are quantified. E3 concluded utility scale batteries are the system marginal resource by 2035, not gas fired generation. However, E3 assumed that gas generation continued to be the marginal resource for local RA in 2035. We urge CAISO to revise its past practice of assuming gas generation is the marginal system resource for both system RA and Local RA in 2035.
Cal Western believes there are also glaring omissions from TEAM methodology Benefits Calculations, for example none of the following have been historically quantified:
- GHG and Renewable Energy Credit (REC) Benefits
- Local Air Emissions benefits (NOx, PM2.5, SOx)
- Reduced Risk of Wildfires
- Reduced need for Aliso Canyon Storage Facility
The E3 study of PTEP economics from 2022 did quantify the avoided REC and GHG benefits but attempting to quantify additional benefits was beyond the scope of the study. Simply adding a reasonable value for PTEPs avoided REC and GHG costs raised the b/c ratio to 0.62-0.68. Again, this b/c ratio did not assume any gas plant retirements in the LA Basin.
Cal Western Grid encourages the CAISO to at a minimum quantify REC and GHG benefits as part of its TEAM evaluation of PTEP in the 2023-24 TPP. CAISO can review the methodology E3 used to evaluate REC and GHG benefits by looking at Cal Western Grid 2022-23 TPP Technical Appendix A (page 32-33) of our Request Window Submission Form submitted on 10/14/22.
Finally, E3 prepared a only a partial update of the economic analysis of PTEP in September 2023 but concluded that given the 2023-24 TPP increased loads and significant new resource additions in the preferred portfolio, the TEAM economic benefits of PTEP would likely be higher than they found in their initial 2022 economic benefits study.
Public Policy Benefits of PTEP - The CAISO evaluation of public policy benefits in the 2022-23 TPP was focused on “Deliverability” and “System Resource Adequacy”. The public policy transmission solutions that were approved in the 2022-23 TPP had the benefit of removing constraints that could hamper bringing clean power from generators to the high voltage 230/500 kV backbone system. However, transmission needed to deliver that power to location constrained load pockets such as the LA Basin was not the focus.
Cal Western Grid applauds the CAISO 2022-23 TPP approval of Public Policy transmission solutions to bring power from renewable energy sources to the high voltage 230/500 kV backbone system, which the CAISO called ‘deliverability’ solutions. However, failing to evaluate and approve transmission solutions that allow renewable power to move from the high voltage 230/500 kV backbone system into transmission constrained load centers is a critical omission that SB 887 requires be addressed.
Cal Western Grid believes that the CPUC is still required to provide gas plant guidance to the CAISO under SB 887, however, CAISO has already received sufficient guidance from the CPUC to proceed with much needed transmission into transmission constrained local areas. The preferred resource portfolio the CPUC has already transmitted to CAISO for the 2023-24 TPP combined with the public policy guidance articulated in SB 887 is sufficient for the CAISO to approve a few initial projects that perform well under multiple scenarios and support reduced reliance on gas plants in transmission constrained load pockets. The only thing CAISO must do is to expand the definition of ‘deliverability’ the way SB 887 requires; Section 1 (h) (3) asks the CAISO to plan and approve transmission that “eliminate(s) transmission constraints that prevent electrical generation resources from delivery to the wider grid and that prevent importing energy into load pockets.”
In the 2022-23 TPP the CAISO approved numerous deliverability solutions that allowed electrical resources to be delivered to the grid. The CAISO did this based on the portfolio provided by the CPUC. What the CAISO failed to do was approve transmission solutions to eliminate transmission constraints that prevent importing energy into load pockets.
It appears to Cal Western Grid that the CAISO is about to repeat this material omission for public policy transmission approvals in the 2023-24 TPP. From the staff overview of Slides 33 and 34 at the 11-16-23 Stakeholder Meeting it appears to Cal Western Grid that CAISO Staff intends to define deliverability narrowly once again, as the ability to deliver power from resources to the high voltage grid, and not address eliminating transmission constraints that prevent importing energy into load pockets. In the 2023-24 TP the CAISO must broaden its definition of deliverability to include transmission needed to bring energy into transmission constrained load pockets.
Turning to the language of SB 887, it is clear the legislature asks CAISO recognize the policies set forth in SB 887:
‘…it is the intent of the Legislature that the Independent System Operator shall take notice of the state policies expressed in this section” SB 887 Section 1 (c).
And Section 1 (h)(3) of SB 887 makes it clear that state policy is to eliminate transmission constraints that prevent importing energy into load pockets (transmission constrained load pockets):
“It is the policy of the state that planning for new transmission facilities considers the following goals: …. (3) eliminate constraints that prevent electrical generation resources from delivering to the wider grid and that prevent importing energy into load pockets.”
And in Section 1 (e) (4) (A) SB 887 provides policy guidance regarding when transmission should be in place to eliminate constraints into local capacity areas, i.e., not later than 2035:
“Providing resource projections that, combined with transmission capacity expansions, are expected to substantially reduce, no later than 2035, the need to rely on nonpreferred resources in local capacity areas.”
The State policy is clear, and the CPUC and CEC have already given load forecasts with a resource portfolio to the CAISO that enables the CAISO to approve the transmission SB 887 Section 1 (h) (3) sets forth as public policy, (i.e., transmission that removes constraints that prevent importing energy into load pockets).
All that is needed is for the CAISO to expand its definition of ‘deliverability’ to embrace the scope required under SB 887. Deliverability that includes both bringing power from resource zones to the high voltage grid and to transmission constrained load pockets.
Cal Western Grid understands that the CAISO has repeatedly asked for gas plant guidance from the CPUC and a plan for reducing reliance on gas generation. Cal Western Grid believes that guidance, including a retirement plan for gas fired generation would facilitate CAISO planning for transmission solutions, but while this required guidance has not been provided, it should not be necessary in order to get started now, in the current 2023-24 TPP, for approving transmission to load centers as envisioned in SB 887.
In fact, waiting for a CPUC gas plant retirement plan is a luxury the CAISO can no longer afford. The 2023-24 TPP resource portfolios provided by the CPUC, once again, do not contain a plan for reducing reliance on gas plants during the planning horizon. Even more concerning is the CPUC on October 5, 2023, issued its proposed preferred planning portfolio for the 2024-25 TPP without any provision for gas plant reductions or guidance for the CAISO.
Again, the CPUC proposed a Preferred Resource Portfolio that does not plan for meaningfully reduced reliance on gas plants in transmission constrained local areas, or even a plan for reducing reliance on system wide gas plants during the entire planning horizon, through 2039.
We urge CAISO recognize the CPUC preferred portfolio that the CPUC has already provided is enough to start approving least regrets transmission solutions that will provide substantial reliability and economic benefits and will be needed to meet California’s SB 887 policy objectives.
As the CAISO knows well, long lead time transmission approved by the CAISO in the 2023-24 TPP is subject to competitive bidding to select a sponsor. We recognize CAISO Management intends to seek Board Approval of major transmission projects at the Board Meeting in May 2024. If a project were approved by CAISO Board in May 2024 as part of the 2023-24 TPP, a sponsor would not, under CAISO’s phase 3 competitive process, be selected until the very end of 2024 or more likely early 2025. Only then can the more than decade-long timeframe for permitting and construction begin. SB 887 requires the Commission to plan to reduce reliance on gas plants in location constrained load centers by 2035. Projects approved by CAISO which do not have a sponsor until early 2025 cannot realistically be expected to be operational by 2035, and the more likely operational date would be in the 2036-2038 timeframe, which fails the policy requirements of the state. This is because the challenge for siting and permitting requirements for significant new transmission projects is long and arduous. This coupled with recent supply chain issues exacerbated by the worldwide growing demand for new transmission cable and equipment that is being driven by the need to reduce reliance on fossil generation.
While Cal Western Grid continues to encourage CAISO to proactively reach out to the CPUC and CEC, Cal Western believes the CAISO can and should make a determination of need for PTEP in this 2023-24 TPP without waiting for further guidance or a gas plant retirement plan from the CPUC.
If CAISO reviews the cumulative benefits of PTEP, even without gas plants being retired, the TEAM methodology alone can drive a b/c ratio that approaches or exceeds 1.0. When the additional reliability benefits, economic benefits that are not quantified in TEAM and urgency to get started with needed policy driven transmission, as required by SB 887 are considered cumulatively, CAISO should conclude approval for PTEP is warranted in the 2023-24 TPP.
Cal Western believes the CAISO approval would receive very little pushback. Multiple stakeholders have filed comments at the CPUC expressing the need to get going with needed new transmission. And importantly, even the CPUC said when transmitting the resource portfolios for the 2023-24 TPP to CAISO:
“If California is to meet its aggressive reliability and environmental goals, more transmission will be needed to be planned and built ahead of generation and storage development, and it is just a matter of exactly when, and not if, the transmission will be needed.”[3]
It is far past time for CAISO to start approving least regrets transmission solutions that will provide substantial reliability and economic benefits that will be needed to meet California’s SB887 policy objectives.
PTEP is a least regrets option that, if triggered in the 2023-24 TPP, can provide a solution to the transmission constrained West LA load pocket and provide substantial economic and reliability benefits.
California Western Grid appreciates the opportunity to offer its views on these critical issues and stands ready to answer any questions or to provide any additional information CAISO may need.
Respectfully submitted,
Marty Walicki, Managing Partner December 4, 2023.
[1] Cal Western has interchangeably used a specific project name (PTEP) and a generic transmission solution described as a subsea transmission project from Central California to Western LA Basin. Cal Western understands the CAISO approves transmission solutions, not specific projects. Cal Western also understands that if a project like PTEP were approved by CAISO the project sponsor would only be selected competitively in the 2023-24 TPP phase three.
[2] Each of these benefits are discussed in more detail in our October 13, 2023, filing.
[3] CPUC Decision 23-02-040, Ordering Supplemental Mid-Term Reliability Procurement (2026-2027) and Transmitting Electric Resource Portfolios to California Independent System Operator for Transmission Planning Portfolios, pp. 48- 49.
New Leaf Energy
Submitted 12/04/2023, 04:36 pm
1.
Please provide your organization’s comments on the Recommended Reliability Projects less than $50 million for the North Region.
New Leaf Energy, Inc. (“NLE”) does not have any comments on this item.
2.
Please provide your organization’s comments on the Recommended Reliability Projects less than $50 million for the South Region.
NLE does not have any comments on this item.
3.
Please provide your organization’s comments on the MIC Expansion Requests.
NLE does not have any comments on this item.
4.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the SCE & GLW areas.
NLE does not have any comments on this item.
5.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the SDG&E area
NLE does not have any comments on this item.
6.
Please provide your organization’s comments on the Preliminary Policy Assessment Results for the PG&E area.
In the comments below, NLE respectfully urges the CAISO to reexamine the Gates-Arco-Midway 230 kilovolt (“kV”) line constraint and the Morro Bay 230 kV line constraint—both of which the CAISO did not propose approving mitigations for during the November 16, 2023 stakeholder meeting for the 2023-2024 Transmission Planning Process (“TPP”). NLE provides several reasons the CAISO should reexamine these constraints before releasing its draft 2023-2024 Transmission Plan.
NLE has redacted all confidential information from the comments below. Concurrently with submitting these comments, NLE transmitted a non-redacted confidential version of the comments to the CAISO.
- Gates-Arco-Midway 230 kV Line Constraint
The Gates-Arco-Midway 230 kV line constraint impacts 90 substations, and nearly a quarter of the CAISO’s queued megawatts (“MW”) of generating capacity through Cluster 14 are behind this constraint alone.[1] The constraint significantly affects proposed projects in the PG&E Fresno and Kern study areas. [REDACTED].[2] [REDACTED].[3] If the CAISO does not approve Gates-Arco-Midway, this constraint will continue to be binding and will prevent Cluster 14 projects in the Kern and Fresno study areas from qualifying for TPD.
Further, approving a mitigation for this policy-driven need would also address identified reliability-driven needs. The CAISO’s preliminary reliability results for the PG&E bulk system identify overloads to the Arco-Midway 230 kV line under a P1 loss of the Gates-Midway 500 kV line, as well as under several P6 outages. Further, the 2024 and 2028 Local Capacity Technical Studies identify Local Capacity Requirement deficiencies in the Kern and Fresno Local Capacity Resource Areas.[4] Approving the mitigation would address these deficiencies and Local Resource Adequacy procurement challenges experienced by the load-serving entities.
Additionally, NLE respectfully urges the CAISO to further analyze the policy-driven studies for the Gates-Arco-Midway 230 kV line. The findings of the policy-driven study performed in the TPP and the studies estimating transmission capability for the California Public Utilities Commission (“CPUC”) do not appear to align. The CAISO released transmission capability estimates—for use in the CPUC’s Integrated Resource Planning (“IRP”) process—indicating that the Midway constraint on the Midway-Q2005 230 kV line, which is a parallel path to the Gates-Arco-Midway 230 kW line, has 1,099 MW of deliverability available for Full Capacity Deliverability Status (“FCDS”) resources.[5] This transmission capability estimate is largely consistent with the results from the 2023 TPD Allocation Report.[6] However, the draft policy-driven studies performed as part of the 2023-2024 TPP do not show a binding constraint for the Gates-Arco-Midway 230 kV line, despite there being significantly more resources proposed behind this constraint than available deliverability.[7] NLE respectfully requests that the CAISO investigate why the results of these studies do not align and why the relevant proposed resources do not trigger a mitigation.
Finally, though the CAISO does not consider environmental justice issues in the context of the TPP initiative, it bears mentioning that there are a disproportionate number of Disadvantaged Communities (“DACs”) located in the Fresno and Kern study areas.[8] If the CAISO does not approve a mitigation for the Gates-Arco-Midway 230 kV line constraint, most projects in these areas would not receive TPD. This would consequently prevent or delay construction of the projects and impede the community, health, and environmental benefits for residents within these DACs.
For the reasons described above, it is essential that the CAISO reexamine the Gates-Arco-Midway 230 kV line constraint. Failing to approve a mitigation for this constraint in the 2023-2024 Transmission Plan would result in Cluster 14 projects in the Kern and Fresno study areas needing to withdraw from the interconnection queue or proceed as Energy Only.[9] This could significantly impact California’s ability to meet its renewable energy and reliability goals, as well as the availability of resources needed to satisfy Local Capacity Requirements.
- Morro Bay 230 kV Line Constraint
NLE respectfully urges the CAISO to further analyze the policy-driven studies for the Morro Bay 230 kV line. The findings of the policy-driven study performed in the TPP and the studies estimating transmission capability for the CPUC do not appear to align. The CAISO’s transmission capability estimates for the CPUC’s IRP process indicate that the Morro Bay Looping has 937 MW of deliverability available for FCDS resources.[10] This transmission capability estimate is fairly consistent with the results from the 2023 TPD Allocation Report.[11] On the other hand, the draft policy-driven studies performed as part of the 2023-2024 TPP do not show a binding constraint for the Morro Bay 230 kV line—despite 2,500 MW of resources within the Morro Bay 230 kV boundary. Although a specific Point of Interconnection is needed to determine the exact amount of deliverability available for FCDS resources, the capacity in the policy-driven studies is over 2.5 times the estimated available deliverability for FCDS resources. The CAISO should therefore revisit the results of these studies.
Additionally, the mitigation for the Morro Bay 230 kV line constraint is a multi-value asset that would address policy- and reliability-driven needs that are critical to address for Cluster 14 projects seeking TPD. NLE’s prior comments on the 2023-2024 TPP reliability results advocate for approving a mitigation for the Morro Bay 230 kV line constraint. The CAISO’s response to comments states that the long-term thermal violations in a post-Estrella Substation configuration were largely driven by load projection at Paso Robles, and the CAISO therefore recommends monitoring load materialization.[12] However, if the CAISO does not approve the mitigation in the 2023-2024 TPP, Cluster 14 projects behind the constraint would not receive deliverability during the next two TPD allocation cycles and would need to proceed as energy-only resources or withdraw from the queue.[13] Furthermore, approval timing will be critical in this cycle due to the timeline required to complete the mitigation.[14]
[1] CPUC, Dashboard for Preliminary Mapping of Proposed 24-25 TPP Base Case, “Res_by_Sub_2034” tab (Oct. 26, 2023), available at: https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/energy-division/documents/integrated-resource-plan-and-long-term-procurement-plan-irp-ltpp/2023-irp-cycle-events-and-materials/assumptions-for-the-2024-2025-tpp/dashboard_prelimmapping_10-26-23.xlsx (There are 105 queued projects totaling 27,721 MW at substations listed under the High System Need Midway - Q2005 230kV constraint (“Gates-Arco-Midway”), and the total CAISO queue through Cluster 14 includes 460 projects totaling 120,585 MW.).
[2] CAISO, Market Participant Portal, Queue Cluster 14 Phase I Interconnection Study Report, PG&E Fresno Interconnection Area Study Report, Appendix I: Deliverability Assessment Results (Sept. 15, 2022); CAISO, Market Participant Portal, Queue Cluster 14 Phase I Interconnection Study Report, PG&E Kern Interconnection Area Study Report, Appendix I: Deliverability Assessment Results (Sept. 15, 2022).
[3] CAISO, 2023 Transmission Plan Deliverability Allocation Report at 41, available at: https://mpp.caiso.com/tp/Documents/2023%20TPD%20Allocation%20Report.pdf.
[4] CAISO, 2024 Local Capacity Technical Study (Apr. 28, 2023), available at: http://www.caiso.com/InitiativeDocuments/Final-2024-Local-Capacity-Technical-Report.pdf; CAISO, 2028 Local Capacity Technical Study (Apr. 28, 2023), available at: http://www.caiso.com/InitiativeDocuments/Final-2028-Long-Term-Local-Capacity-Technical-Report.pdf.
[5] CAISO, Transmission Capability Estimates for Use in the CPUC’s Integrated Resource Planning Process (June 29, 2023), available at: https://www.caiso.com/Documents/Transmission-Capability-Estimates-for-use-in-the-CPUCs-Integrated-Resource-Planning-Process.xlsx (based on studying on-peak resources).
[6] CAISO, 2023 Transmission Plan Deliverability Allocation Report at 41, https://mpp.caiso.com/tp/Documents/2023%20TPD%20Allocation%20Report.pdf ([REDACTED]).
[7] CAISO, 2023-2024 Transmission Planning Process Stakeholder Meeting Presentation at 141-143, 151-153 (Nov. 16, 2023), available at: http://www.caiso.com/InitiativeDocuments/Presentation-2023-2024-Transmission-Planning-Process-Nov16223.pdf.
[8] California Office of Environmental Health Hazard Assessment, SB 535 Disadvantaged Communities, https://oehha.ca.gov/calenviroscreen/sb535.
[9] [REDACTED].
[10] CAISO, Transmission Capability Estimates for Use in the CPUC’s Integrated Resource Planning Process (June 29, 2023), available at: https://www.caiso.com/Documents/Transmission-Capability-Estimates-for-use-in-the-CPUCs-Integrated-Resource-Planning-Process.xlsx (based on studying on-peak resources).
[11] CAISO, 2023 Transmission Plan Deliverability Allocation Report at 38, https://mpp.caiso.com/tp/Documents/2023%20TPD%20Allocation%20Report.pdf ([REDACTED]).
[12] CAISO, Response to Stakeholder Comments from 2023-2024 Transmission Planning Process Stakeholder Meeting (Sept. 26-27, 2023), available at: https://www.caiso.com/InitiativeDocuments/ISOResponsestoComments-2023-2024TransmissionPlanningProcess-Sep26-27-2023.pdf.
[13] CAISO, Market Participant Portal, Queue Cluster 14 Phase I Interconnection Study Report, PG&E Kern Interconnection Area Study Report, Appendix I: Deliverability Assessment Results (Sept. 15, 2022) ([REDACTED]).
[14] CAISO, Market Participant Portal, Queue Cluster 14 Phase I Interconnection Study Report, PG&E Kern Interconnection Area Final Report - Revision 1 (Nov. 4, 2022) [REDACTED]).
7.
Please provide your organization’s comments on the Preliminary Economic Analysis Results.
NLE does not have any comments on this item.
8.
Please provide any additional comments on the November 16, 2023 Transmission Planning Process Stakeholder Meeting.
NLE respectfully requests that the CAISO promptly post the policy-driven base cases to the Market Participant Portal, along with the TARA input files required to run deliverability assessments. The CAISO should provide stakeholders with access to this data as soon as possible—rather than posting the data and the draft transmission plan in the same month as has been done in the past. Posting the base cases and underlying data expeditiously would ensure stakeholders have sufficient time to provide informed and useful feedback in the TPP initiative.