1.
Please provide a summary of your organization’s comments on the 2023 Interconnection Process Enhancements (IPE) track 2 discussion paper and stakeholder call.
Vistra appreciates the CAISO launching track 2 of the Interconnection Process Enhancements 2023 effort exploring comprehensive reforms aimed at curing the overheated queue issue. We respectfully submit these high-level comments on the principles, problem statement, concepts put forward by the CAISO.
Background
Vistra is a leading, Fortune 500 integrated retail electricity and power generation company based in Irving, Texas, providing essential resources for customers, commerce, and communities as the nation’s largest competitive power provider and one of the nation’s largest competitive retail providers. In California, Vistra and its subsidiary Dynegy Marketing & Trade (Vistra) own and operate 110 MW of jet-fuel combustion turbines at its Oakland Power Plant, 1,020 MW of efficient combined cycle gas turbines at its Moss Landing Power Plant, and 750 MW / 3,000 MWh of energy storage at its Moss Landing Energy Storage Facility. Through its subsidiaries, Vistra operates the Moss Landing Energy Storage Facility and the Moss Landing Power Plant to provide Resource Adequacy (RA) capacity and energy and ancillary services (E&AS) to the grid.
More relevant to this effort, Vistra is currently developing up to an additional 1,260 MW / 5,040 MWh of combined storage projects at our fully owned and controlled Oakland[1], Moss Landing, and Morro Bay sites to provide Resource Adequacy (“RA”) capacity and E&AS. Vistra is exploring additional development opportunities for clean energy or carbon neutral new resources to help advance California’s reliability and energy goals. Any future projects will need Full Capacity Deliverability Status (FCDS) so that they can provide both RA and E&AS services, without the FCDS any future projects will most likely be unviable. Through the interconnection process, any future project needs to receive Transmission Plan Deliverability (TPD) allocations to afford it FCDS, which is required to submit an offer into solicitations for RA.[2]
This is the chicken and egg problem. Non-utility developers (majority of developers) need TPD allocated to a project for that project to receive FCDS, where FCDS is required to be able to offer into a long-term RA solicitation a new project with the rights to sell RA. If the interconnection rules require having already sold RA to gain priority to those rights but the non-utility developer has no rights to sell RA, then the non-utility developer cannot participate in the long-term RA solicitations to execute the contracts to gain priority because it does not have the priority. The interconnection process’ chicken and egg problem.
As a non-utility developer, owner, and operator, Vistra is developing resources providing long-term RA services to our Load Serving Entity partners. We retain the ownership and operation of our assets, which is critical to bringing cost-competitive offers to our partners because the projected E&AS value allows a more competitive long-term RA offer. We bring value to California resource procurement activities through our credibility, demonstrated performance, and risk management practices. These advantages allow us to bring cost-competitive and proven solutions to our partners if a project can receive TPD to support FCDS. However, Vistra has faced challenges with advancing projects needing deliverability due to being a non-utility developer.
The CAISO’s various interconnection enhancements in recent years have erected barriers for non-utility developers seeking to interconnect new projects to the grid.
Non-utility developers are unable or unwilling to take risks associated with participating in solicitations without achieving TPD allocations, which are necessary pre-requisite to receiving FCDS in order to sell RA. In this respect, non-utility developers are placed at a competitive disadvantage with utilities and end-use customers. It seems to us that non-utility developer projects are deprioritized seemingly solely because we are neither a utility or end-use customer.[3] Utilities that are also Interconnection Customers (IC) do not face the same challenge because CAISO has a long standing practice of preferencing utility developers where it “has always been CAISO policy to avoid utilities needing to execute agreements with themselves or petition the Commission for waiver to meet CAISO requirements”.[4] Similarly, we believe that end-use customer developers were afforded a path to support they are serving their own load.[5]
Our challenges with rules that disadvantage non-utility developers’ ability to compete for TPD and that deprioritize site control or permitting progress as criteria for “first ready” are exacerbated by (1) a combination of an overheated interconnection queue and (2) limited headroom available to facilitate interconnections for full capacity deliverability status. As such, we agree with the CAISO that there are issues with the interconnection process, as well as resource planning and transmission planning processes, that merit a deep consideration of the issues facing all market participants and identifying solutions that get to the root of the market participants’ issues.
Problem Statements (Section 1)
At a high level, Vistra agrees with the two “problem statements” identified by CAISO. But, Vistra believes that the working group discussions need to get at the heart of what problems are preventing projects from advancing through the interconnection process, rather than focusing on the result of the underlying issues of too many interconnection requests and projects staying in the queue without reasonable prospects of timely development.
Vistra recommends that the focus of the June 20th and June 21st working group should be to scope out the underlying issues resulting in excessive amounts of interconnection requests and hampering interconnection requests ability to move timely through the study process, regardless of whether they occur under forward resource planning processes, transmission planning processes, or under the interconnection processes. We request the CAISO facilitate discussions between Interconnection Customers, whether a Load Serving Entity, End-Use Customer, or non-utility developer, on their unique experiences or challenges procuring or developing viable, cost-competitive projects. Out of this discussion, Vistra hopes the CAISO will categorize the types of issues developers are facing, and whether they are resource planning-related, transmission-related, or interconnection-related, and whether they are within the CAISO or CPUC scope, so that the underlying issues can be appropriately addressed. While Vistra had hoped the initial working groups in this effort would be joint CPUC and CAISO workshops because the underlying issues span both agencies, this approach could help meet that need.
Principles (Section 3)
First, Vistra requests the CAISO specify in its revised principles that the interconnection process should maintain open access and avoid unduly discriminatory or preferential treatment. Preferencing utility development or end-use customer development over non-utility development unduly discriminates against non-utility developers. Rules that define priority based on the type of market participant rather than independent eligibility criteria are on its face preferential. [6] We hope the CAISO will commit in this track to prioritize processes that allow open access and do not unduly advantage certain market participants over others. [7]
Second, Vistra requests the CAISO clarify its principle that CAISO’s interconnection processes should “prioritize interconnection in zones where transmission capacity exists or new transmission has been approved.” Regardless of the nature of the transmission project from the reliability, policy, or economic studies. The CAISO should be indifferent as to which type of transmission projects result in increasing the headroom on the system to support new resource interconnection. For example, if an economic study project results in increasing the deliverability capability on the grid above that which the policy portfolios themselves through either reliability or policy studies would have provided because this could further increase the available headroom.
Third, Vistra requests the CAISO add a principle similar to that the CAISO’s transmission or interconnection processes should allow for Interconnection Customers or other agencies with transmission funding to “subscribe” to partially fund network upgrades (NU) needed to facilitate new resource interconnection so that new transmission upgrades can be proposed and collectively funded. This principle will allow for the CAISO’s first principle on prioritizing interconnection in areas where transmission is available, because it affords a fair mechanism to ensure sufficient transmission exists or is planned. If there is such a mechanism, then there can be more confidence in any proposals that hinge on limiting interconnections to some proportion of existing or planning capability. Further, there is a need to consider how state or federal transmission funding could be used to fund specific transmission projects and this principle would allow for consideration of mechanisms to afford a path for projects or programs that are committed to achieve commercial operations or awarding grants to support commercial operations to have a path to fund network upgrades to support their interconnection. Concepts such as prioritizing TPD allocations based on willingness to subscribe to offset network upgrade costs that resulted in the TPD would be consistent with this type of principle.
Vistra will continue to consider what principles should be adopted in this effort and bring additional thoughts to the working group meetings.
[1] Re-development of Oakland Power Plant would also facilitate the repowering of its jet fuel-fired Oakland Power Plant with carbon neutral energy storage to further the retirement of the remaining units.
[2] Given Vistra’s belief that FCDS is required to participate in Integrated Resource Planning or Central Procurement Entity solicitations that could procure a new resource under long-term RA agreements, Vistra believes the CAISO existing TPD allocation groups in practice do not actually mean that allocation group A includes projects that have executed a Power Purchase Agreement, but instead that it only includes projects that are submitted by utility developers and potentially end-use customer developers. These types of developers get priority over non-utility developers by virtue of these entities’ type of entity rather than eligibility criteria, because non-utility developers seeking FCDS also intend for the project to provide RA.
[3] Notably, one such example is our efforts to redevelop mothballed generating facilities at our fully owned and controlled Morro Bay site where we hold 100% site control, are located next to existing interconnection and transmission facilities, and are advancing timely through environmental permitting processes. This project should be considered viable, but because we are a third-party developer instead of a utility or end-use customer it is seemingly being considered “speculative”. We question if this is truly CAISO’s intent, and if not, this reform should correct this signal.
[4] CAISO Transmittal Letter, ER22-2018, June 2, 2022, footnote 33.
[5] CAISO Transmittal Letter, ER23-941, January 26, 2023, Page 7 and Page 26.
[6] CAISO’s rule changes in recent years have shown a shifting towards limiting non-utility corporations ability to develop projects to successfully receive an allocation to support full capacity deliverability status (FCDS) such that we can offer the projects into the procurement solicitations. See Vistra’s Initial Comments on Interconnection NOPR under RM22-14 discussing this principled position in more detail, October 13, 2022, Page 8-11, https://elibrary.ferc.gov/eLibrary/filedownload?fileid=B30BD723-CFC2-CEC2-85ED-83D310200000.
[7] Vistra acknowledges that FERC has approved the existing preferential rules because there was an insufficient record to find them unduly preferential. In this process, we are asking the CAISO to avoid this challenge altogether by avoiding rules that would differentiate access based on the type of market participant, and instead pursue rules that are unbiased and independent. This will create a smooth pathway through the FERC review process.
5.
If your organization would like to present a proposal on an alternative methodology for accomplishing the fundamental principles in the discussion paper at an upcoming working group meeting, please provide a summary of your proposal, including a statement on how the proposal addresses the problems identified and adheres to the principles outlined in the discussion paper and stakeholder comment.
Vistra believes the interconnection reforms should adopt a non-discriminatory, first-ready, first served approach. We support rules that disincentivize developers submitting speculative projects that are less viable or not commercial ready as well as to disincentivize parking excessively in the queue. CAISO’s interconnection processes need to better advance commercially viable projects from any type of Interconnection Customer ensuring non-discriminatory, open access that best supports California needs and disincentives submitting non-commercially viable projects. It also needs to create an environment where projects are willing to withdraw or downsize if they receive information indicating they are not viable.
Vistra has submitted comments on the CAISO and FERC processes over the last two years providing significant feedback and proposals on interconnection and transmission enhancements. Our current thinking is to present an updated version of our proposals described in both FERC and CAISO filings highlighted below.
- Optional feasibility cluster separate and parallel to common cluster: Adding optional feasibility clusters similar to those offered in other markets as a mechanism to provide “speculative” projects the information they are seeking in a much higher level, faster feasibility study outside the normal cluster process that would not require a withdrawal decision because this low cost path to receive feasibility information is opted into in lieu of the common cluster studies at a much higher cost cluster study process that would progress to phase I and II studies.[1]
- Network upgrade open season/subscription model available to Interconnection Customers (IC) and other eligible parties: Adding open seasons for IC or other eligible and interested parties such as federal or state grant programs to subscribe to network upgrades in the transmission planning processes, where the IC or state agency would receive a commensurate share of the increased deliverability relative to their share of the network upgrades. Vistra believes this approach has significant benefits because it also allows a Tariff codified process for the federal and state funding that have been identified for transmission projects that currently have no mechanism to provide that funding to CAISO to support a portion of any network upgrades for resource interconnections.
Please review our previously filed comments on “open seasons” for more detail. [2]
[1] Vistra Comments on the Interconnection Process Enhancements 2021 preliminary issue paper and stakeholder workshop, November 5, 2021, response to #3 describes some first ready enhancements, https://stakeholdercenter.caiso.com/Comments/AllComments/93e0040c-4e2e-4d37-8b2c-7eb0e7c55aa9#org-f382caf5-b32a-43e5-a759-fe484ea5d2c2.
[2] Vistra’s Initial Comments on Transmission and Interconnection ANOPR under RM21-17, October, 12, 2021, https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20211012-5513; Vistra’s ANOPR Reply Comments on RM21-17, November 30, 2021, https://elibrary.ferc.gov/eLibrary/filedownload?fileid=FF0FAB4D-FEEE-C055-9F6F-7D7262400000; Vistra’s comments on Interconnection Process Enhancements 2021 phase 1 issue paper and straw proposal, Page 6-10 on concepts for cluster 15 and beyond, January 18, 2022, https://stakeholdercenter.caiso.com/Comments/AllComments/fb35aeb3-10f4-4351-9232-040ec49cfd84#org-35e3746d-a302-4bf3-971d-48a6735f097c; Vistra’s Initial Comments under RM21-17, August 17, 2022, https://elibrary.ferc.gov/eLibrary/filedownload?fileid=45A5B320-C13F-CFD0-A657-82AD8C200000; Vistra’s comments on transmission planning process enhancements straw proposal, October 17, 2022, response to number 3 includes a discussion of need for transmission network upgrade open seasons, https://stakeholdercenter.caiso.com/Comments/AllComments/fe469961-883e-4454-9adb-44eb6098b450#org-463be33a-5eca-42c9-a5d3-57d55167d637.