This release introduces enhancements to include behind the meter data along within gross load metering submissions by the Scheduling Coordinators, enhance ISO settlement configurations to accommodate this added information, publish a performance report, as well as provide a feedback loop for the demand forecast model to consider excess behind the meter production.
Outcome: This initiative integrated a new measurement type into Settlements and adjusted reliability-related charges by including behind-the-meter data within gross load metering submissions by scheduling coordinators.
Proposal Development | Decision | Implementation | Completed/Closed |
---|---|---|---|
Dec 02, 2019 Revised draft tariff language
Dec 19, 2018 Draft final proposal |
Dec 23, 2020 FERC approval (ER21-190)
Oct 23, 2020 Tariff amendment filing (ER21-190) May 15, 2019 Board of Governors approval |
Oct 01, 2020 Deployment
Jan 2021 Activation |
Completed |