This initiative will address the California ISO’s compliance with FERC Order No. 881 in establishing new transmission line rating requirements
Proposal Development | Decision | Implementation | Completed/Closed | |
---|---|---|---|---|
Phase 2 |
Jul 23, 2024 Working group
|
Jun 16, 2023 Compliance Filing (ER22-2362)
|
Apr 24, 2024 Data submission working group
Implementation milestones
Apr 01, 2024 - track 1 Q4 2024 - track 2 |
|
Phase 1 |
Jun 23, 2022 Revised draft tariff language posted
|
Apr 20, 2023 FERC approval (ER22-2362)
Jul 12, 2022 Compliance filing (ER22-2362) |
Through Phase 2 of this initiative, the ISO will coordinate with participating transmission owners, WEIM entities, market participants, and RC West customers to address implementation issues and milestones associated with new transmission line rating requirements under Order No. 881.
This initiative will address the California ISO’s compliance with FERC Order No. 881 in establishing new transmission line rating requirements