This initiative will review the Reliability Must-Run (RMR) tariff, agreement and process, and will seek to clarify RMR procurement versus backstop procurement under the Capacity Procurement Mechanism (CPM). The initiative is planned in two phases: 1) focus on developing a must-offer obligation for RMR units, and 2) identify potential refinements and strive to unify RMR and CPM under a single procurement framework.
Proposal Development | Decision | Implementation | Completed/Closed |
---|---|---|---|
Apr 03, 2019 Third revised draft tariff language posted
Jan 23, 2019 Draft final proposal posted |
Oct 28, 2019 Compliance filing (ER19-1641)
Sep 27, 2019 FERC approval Apr 22, 2019 Tariff amendment filing (ER19-1641) Mar 27, 2019 Board of Governors approval |
Nov 13, 2019 Deployment
Jan 2020 Activation |
Completed |